Contract Termination Procedures
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Executives
Purpose
Establish procedures for handling contract terminations, whether initiated by owner or contractor.
⚠️ IMPORTANT
Contract termination has serious legal and financial consequences. Always consult legal counsel before terminating or responding to termination.
Types of Termination
Termination for Cause
- One party breaches contract
- Other party terminates due to breach
- Specific grounds required
- Notice and cure period typically required
Termination for Convenience
- Owner terminates without cause
- Contractor entitled to costs incurred
- Plus reasonable profit on work performed
- Common in public contracts
Mutual Termination
- Both parties agree to end contract
- Terms negotiated
- Settlement agreement executed
Grounds for Termination (Typical)
Owner May Terminate Contractor For:
- Failure to prosecute work
- Failure to pay subcontractors/suppliers
- Persistent safety violations
- Abandonment of work
- Failure to maintain schedule
- Insolvency/bankruptcy
- Material breach of contract
Contractor May Terminate For:
- Non-payment (after notice and cure)
- Extended suspension of work
- Owner's material breach
- Failure to provide access
- Unsafe conditions (owner-caused)
Termination for Cause Process
If Receiving Notice of Default:
Step 1: Review Notice Carefully
- What breach is alleged?
- Is it accurate?
- What cure period?
- What contract provision?
Step 2: Respond Immediately
- Acknowledge receipt
- Dispute inaccuracies
- Outline corrective action
- Request meeting
Step 3: Cure if Possible
- Address legitimate issues
- Document corrective actions
- Provide evidence of cure
- Request withdrawal of notice
Step 4: If Termination Occurs
- Protect your rights
- Document everything
- Preserve records
- Engage legal counsel
- Consider counterclaims
If Issuing Notice of Default:
Step 1: Verify Grounds
- Document breach thoroughly
- Confirm contract allows termination
- Consult legal counsel
- Consider alternatives
Step 2: Issue Notice
- Written notice per contract
- Specific about breach
- Cite contract provision
- State cure period
- State consequences
Step 3: Monitor Cure Period
- Document any response
- Track cure efforts
- Maintain records
Step 4: If No Cure
- Issue termination notice
- Per contract requirements
- Document basis
- Prepare for transition
Termination for Convenience
Owner Terminates - Contractor Rights:
Typically Entitled To:
- Payment for work completed
- Cost of materials ordered
- Demobilization costs
- Reasonable profit on work performed
- Overhead on uncompleted work (varies)
Typically NOT Entitled To:
- Anticipated profit on unperformed work
- Consequential damages
Process:
- Receive termination notice
- Stop work as directed
- Protect work in place
- Inventory materials
- Document costs
- Submit termination claim
- Negotiate settlement
Termination Checklist
Immediately Upon Termination:
Secure the Site:
- Remove company equipment
- Secure materials
- Protect work in place
- Document conditions (photos)
- Secure records
Notify:
- Subcontractors
- Suppliers
- Bonding company
- Insurance company
- Legal counsel
Document:
- Work completed
- Materials on site
- Materials ordered
- Work in progress
- Percentage complete
- Cost to date
- Remaining costs
Financial:
- Final pay application
- Retain cost records
- Track additional costs
- Preserve lien rights
Termination Claim Components
For Convenience Termination:
1. Contract Price $__________
2. Less: Previous Payments $__________
3. Cost of Work Performed $__________
4. Cost of Materials (on-site) $__________
5. Cost of Materials (in transit) $__________
6. Cost of Materials (ordered) $__________
7. Demobilization Costs $__________
8. Profit on Work Performed $__________
9. Overhead Allocation $__________
10. Settlement Costs $__________
─────────────────────────────────
TOTAL TERMINATION CLAIM $__________
Subcontractor Termination
When Terminating a Subcontractor:
Before Terminating:
- Review subcontract terms
- Document deficiencies
- Issue written notice
- Allow cure period
- Consult with counsel
Process:
- Issue default notice
- Document lack of cure
- Issue termination notice
- Notify bonding company (if bonded)
- Backcharge as appropriate
- Engage replacement
- Document all costs
Dispute Resolution
If Termination is Disputed:
Options:
- Negotiation
- Mediation
- Arbitration
- Litigation
Preserve Rights:
- Continue documenting
- Preserve all records
- Meet all deadlines
- Reserve all claims
Related Documents
- Contract Review Checklist
- Claims Procedures
- Notice Requirements
- Subcontractor Management
Template provided by support.construction. Always consult legal counsel for termination matters.