Submittal Process

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Project Engineers, Superintendents


Purpose

Establish a consistent process for preparing, reviewing, transmitting, and tracking submittals to ensure materials and systems comply with contract requirements.


What is a Submittal?

A submittal is a document (shop drawing, product data, sample, etc.) provided by the contractor for the architect/engineer to review for conformance with the design intent.

Types of Submittals

TypeDescriptionExamples
Shop DrawingsDetailed drawings for fabricationSteel, millwork, mechanical
Product DataManufacturer specificationsCut sheets, spec sheets
SamplesPhysical samples of materialsFinishes, colors, textures
CertificatesTest reports, certificationsConcrete mix, steel certs
O&M ManualsOperation and maintenance infoEquipment manuals
WarrantiesManufacturer warrantiesRoofing, equipment

Submittal Process Overview

Specification Review → Submittal Schedule → 
Subcontractor Preparation → Contractor Review →
Transmit to A/E → A/E Review → Receive Response →
Distribute → Fabricate/Procure

Step-by-Step Process

Step 1: Create Submittal Schedule

At Project Start:

  1. Review specifications for submittal requirements
  2. Identify all required submittals by spec section
  3. Determine required review time
  4. Work backwards from installation dates
  5. Identify long-lead items

Submittal Schedule Content:

  • Submittal number
  • Description
  • Spec section
  • Responsible party (sub)
  • Date due to GC
  • Date due to A/E
  • Approval needed by
  • Lead time after approval

Step 2: Subcontractor Submittal Preparation

Subcontractor Responsibilities:

  • Prepare complete submittals
  • Review for compliance with contract
  • Include all required information
  • Submit to GC on schedule

Submittal Package Must Include:

  • Cover sheet/transmittal
  • Relevant spec sections highlighted
  • Product data (complete, not excerpts)
  • Shop drawings (stamped by PE if required)
  • Samples (as specified)
  • Certifications

Step 3: Contractor Review

GC Review Checklist:

Before transmitting to A/E:

  • Submittal is complete
  • Correct products specified
  • Matches contract requirements
  • Dimensional accuracy verified
  • Field conditions considered
  • Coordination with other trades reviewed
  • Required certifications included
  • Properly stamped (if required)

Contractor's Stamp:

CONTRACTOR'S REVIEW STAMP

[Company Name]
[Project Name]

☐ Approved
☐ Approved as Noted
☐ Revise and Resubmit
☐ Rejected

Reviewed By: _____________ Date: _______

This review is for general conformance with the
design concept. Contractor is responsible for
dimensions, quantities, and coordination.

Step 4: Transmit to Architect/Engineer

Submittal Transmittal Must Include:

  • Transmittal number
  • Date
  • Project name/number
  • Submittal number
  • Description
  • Spec section reference
  • Number of copies
  • Purpose (for approval, for information)

Submit To:

  • Per contract requirements
  • Typically Architect with copy to Owner
  • Use required distribution

Methods:

  • Project management system (preferred)
  • Electronic submission (PDF)
  • Hard copy (if required)

Step 5: A/E Review Period

Standard Review Time:

  • Per contract (typically 10-14 business days)
  • First review longer than resubmittals
  • Track against required schedule

Follow-Up:

  • Contact if exceeding review period
  • Document delays
  • Escalate to owner if significant

Step 6: Receive and Process Response

Review Actions (A/E):

ActionMeaningNext Step
ApprovedNo changes neededProceed to fabricate
Approved as NotedMinor changesMake changes, proceed
Revise and ResubmitSignificant issuesCorrect and resubmit
RejectedDoes not complyMajor revision required
For Information OnlyNo formal actionFile

Upon Receipt:

  1. Log response date
  2. Review comments thoroughly
  3. Verify action required
  4. Distribute to affected parties
  5. Monitor resubmittal if required

Step 7: Distribute Approved Submittals

Distribute To:

  • Subcontractor (for fabrication)
  • Superintendent (for verification)
  • Project file (official record)
  • Others as needed

Ensure:

  • Current revision is distributed
  • Outdated versions removed
  • Field has access to approved submittals

Step 8: Track Resubmittals

If Resubmittal Required:

  1. Communicate comments to sub
  2. Set deadline for resubmission
  3. Track as new revision
  4. Repeat review process

Number Revisions:

  • Original: 001
  • First revision: 001-R1
  • Second revision: 001-R2

Submittal Log Template

Sub #DescriptionSpecSubDue to GCDue to A/ESentStatusApprovedLead
03-001Concrete Mix Design03300ABC1/101/151/12Approved1/253 days
05-001Structural Steel05120XYZ1/151/201/22Rev/Resub12 wks
07-001Roofing07500Acme1/201/25Pending6 wks

Submittal Transmittal Form

================================================================
SUBMITTAL TRANSMITTAL
================================================================

TRANSMITTAL NO: ____________ DATE: ____________

PROJECT: ________________________ PROJECT #: ____________

FROM: [Your Company]
TO: [Architect/Engineer]

================================================================

SUBMITTAL INFORMATION:

Submittal No: ____________ Revision: ____________

Specification Section: ____________

Description: ________________________________________________

Submitted By (Subcontractor/Supplier): ______________________

================================================================

PURPOSE:
☐ For Approval
☐ For Information Only
☐ Resubmittal (Previous #: ________)

CONTENTS:
☐ Shop Drawings Copies: _____ Sheets: _____
☐ Product Data Pages: _____
☐ Samples Quantity: _____
☐ Certificates Pages: _____
☐ Other: _______________

================================================================

CONTRACTOR'S REVIEW:

☐ Approved
☐ Approved as Noted (see attached)
☐ Rejected (see comments)

Comments: __________________________________________________
___________________________________________________________

Reviewed By: _________________________ Date: ____________

================================================================

RESPONSE REQUIRED BY: ____________

[Note: Installation scheduled for ____________. Delayed
response may impact project schedule.]

================================================================

Long-Lead Submittals

Identify Early:

Items typically requiring extended lead times:

  • Structural steel (8-16 weeks)
  • Elevators (16-24 weeks)
  • Custom millwork (8-12 weeks)
  • Mechanical equipment (10-20 weeks)
  • Electrical switchgear (12-20 weeks)
  • Fire alarm systems (8-12 weeks)
  • Custom doors/frames (6-12 weeks)
  • Specialty glass (8-14 weeks)

Expedite Process:

  1. Identify at project start
  2. Issue to subs first
  3. Expedite review internally
  4. Request expedited A/E review
  5. Track closely
  6. Escalate delays immediately

Submittal Review Best Practices

Contractor Review Focus:

Dimensional:

  • Fits available space
  • Coordinates with other trades
  • Field measurements verified

Performance:

  • Meets specification requirements
  • Appropriate for application
  • Code compliant

Coordination:

  • Works with adjacent systems
  • No conflicts identified
  • Interface details addressed

Completeness:

  • All required information included
  • Samples/color selections included
  • Certifications attached

Common Submittal Mistakes

Avoid:

  • Submitting without review
  • Incomplete packages
  • Wrong products
  • Missing samples/color selections
  • Late submissions
  • Not tracking resubmittals
  • Field proceeding without approval

Best Practices:

  • Review specifications thoroughly
  • Complete packages first time
  • Follow up consistently
  • Track all submittals in log
  • Never fabricate without approval
  • Distribute promptly when approved

  • RFI Process
  • Document Control Procedure
  • Project Startup Procedure
  • Long-Lead Procurement

Software Integration

BLDR Pro Features:

  • Submittal tracking
  • Deadline management
  • Document attachment
  • Review workflow
  • Notification automation
  • Log generation

Template provided by support.construction. Customize with your company information.