Skip to main content
Skip to main content

Daily Reporting Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Superintendents, Foremen, Project Managers


Purpose

Establish requirements for comprehensive daily reporting to document project progress, protect against claims, support billing, and enable management oversight.


Why Daily Reports Matter

"The daily report is your most important legal document."

Daily reports are used for:

  • Defending against delay claims
  • Supporting change order requests
  • Documenting scope completion for billing
  • Identifying productivity issues
  • Tracking weather impacts
  • Recording safety observations
  • Creating an audit trail

Daily Report Requirements

When: Every Work Day

  • Complete before leaving site
  • Submit by end of shift
  • No exceptions (even slow days)

Who:

  • Superintendent (primary)
  • Foreman (trade-specific supplement)
  • PM reviews and archives

Required Daily Report Content

Section 1: Header Information

FieldExample
DateMonday, February 1, 2026
Project NameDowntown Office Building
Project NumberPRJ-2026-001
Report NumberDR-045
Prepared ByJohn Smith, Superintendent

Section 2: Weather Conditions

Record at minimum twice daily:

TimeTempConditionsWindPrecip
7:00 AM45°FOvercast5 mphNone
12:00 PM58°FPartly Cloudy10 mphNone
3:00 PM55°FCloudy15 mphLight rain

Weather Impact:

  • Did weather affect work? Yes/No
  • If yes, describe impact
  • Crews affected
  • Time lost

Section 3: Manpower

Self-Performed Work:

Trade/PositionCountHoursCost Code
Superintendent11001-100
Foreman21803-200
Carpenter64803-200
Laborer43203-200
TOTAL13108

Subcontractor Manpower:

SubcontractorTradeCountHoursLocation
ABC ElectricElectrical432Level 2
XYZ PlumbingPlumbing324Level 1-3
Acme SteelIronworkers648Roof
TOTAL13104

Section 4: Work Performed

Be Specific! Use:

  • Quantities (LF, SF, CY, EA)
  • Locations (grid lines, rooms, floors)
  • Activities (not just "worked on building")

Example Entries:

Bad: "Continued concrete work"

Good: "Placed 85 CY of 4000 PSI concrete for Level 3 suspended slab, grid A-F, lines 1-6. Finished by 2:00 PM, began wet cure."

Work Performed Format:

Area/LocationWork DescriptionQtyUnit
Level 3, A-F/1-6Concrete placement, suspended slab85CY
Level 2, CoreForm stripping, columns8EA
Level 1, Stair 1Metal pan stair installation2Flights

Section 5: Materials Received

SupplierMaterialQtyUnitTicket #Condition
ABC Ready Mix4000 PSI Concrete85CY45678OK
Steel SupplyW12x26 Beams12EA789011 damaged

Note any issues:

  • Short shipments
  • Damaged materials
  • Wrong items
  • Rejection/return needed

Section 6: Equipment on Site

EquipmentOperatorHoursCondition
Crane, 75TJ. Johnson8Operational
Concrete PumpSubcontract6Operational
ForkliftR. Smith6Operational

Equipment Issues:

  • Down equipment
  • Needed equipment not available
  • Maintenance required

Section 7: Visitors and Inspections

TimeNameCompanyPurposeResult
9:00 AMTom BrownCity BuildingFooting inspectionApproved
10:30 AMJane DoeABC ArchitectSite visitQuestions on finish
2:00 PMBob WhiteOwnerProgress walkNo issues

Inspection Results:

  • Passed/approved
  • Failed (reason and corrective action)
  • Re-inspection needed

Section 8: Issues, Delays, and Impacts

Document Any:

  • Delays and causes
  • Access issues
  • Design questions/conflicts
  • Subcontractor issues
  • Owner-caused delays
  • Material issues
  • Utility problems

Example:

ISSUE: Electrical rough-in delayed 
CAUSE: RFI #23 response not received (submitted 1/15)
IMPACT: Cannot close walls in Level 2 offices
ACTION: PM to follow up with architect

Section 9: Safety Observations

ItemObservationAction Taken
HousekeepingGood - all areas cleanN/A
PPE Compliance100% observedN/A
Hazard FoundOpen floor penetration Level 2Covered and barricaded
Near MissN/AN/A
Toolbox TalkYes - Fall Protection23 attendees

Section 10: Tomorrow's Plan

AreaPlanned WorkCrew NeededMaterials Needed
Level 3Cure concrete, layout for embeds2 CarpLayout equipment
Level 2Continue framing4 CarpMetal studs
Level 1Electrical rough4 Elec (sub)Per sub

Coordination Notes:

  • Concrete delivery scheduled 7:00 AM
  • Crane needed for steel 9:00 AM - 12:00 PM
  • Inspector scheduled 10:00 AM

Section 11: Photos

Minimum Photo Requirements:

Photo TypeMinimumDescription
Overall site2AM and PM conditions
Work in progress3-5Each active area
Deliveries1 perMaterial received
IssuesAs neededDocument problems
Concealed workRequiredBefore covering

Photo Standards:

  • Include reference point (scale, location marker)
  • Capture date/time stamp
  • GPS location if possible
  • Add description/caption

Daily Report Submission

Deadline

  • Submit by end of shift
  • No later than 7:00 AM next business day

Submission Method

  • BLDR Pro (preferred)
  • Email with photos attached
  • Cloud folder upload

Review Process

  1. Superintendent completes report
  2. PM reviews next morning
  3. PM addresses any issues
  4. Report archived in project folder

Daily Report Template

=====================================
DAILY CONSTRUCTION REPORT
=====================================

Project: _________________________
Project #: ____________ Report #: ______
Date: _______________ Day: ___________
Prepared By: ______________________

WEATHER:
AM: ___°F / Conditions: ____________
PM: ___°F / Conditions: ____________
Weather Impact: ☐ Yes ☐ No
If yes: __________________________

MANPOWER:
Company Personnel: _____ Total Hours: _____
Subcontractors: _____ Total Hours: _____
TOTAL ON SITE: _____

WORK PERFORMED TODAY:
1. ________________________________
2. ________________________________
3. ________________________________
4. ________________________________

MATERIALS RECEIVED:
________________________________
________________________________

VISITORS/INSPECTIONS:
________________________________
________________________________

ISSUES/DELAYS:
________________________________
________________________________

SAFETY OBSERVATIONS:
Toolbox Talk: ☐ Yes Topic: _________
Hazards Found: __________________
Incidents: ☐ None ☐ Yes (report attached)

TOMORROW'S PLAN:
________________________________
________________________________

PHOTOS ATTACHED: ☐ Yes (#_____)

Signature: _____________ Date: _____

=====================================

Common Daily Report Mistakes

Avoid:

  • Vague descriptions ("worked on project")
  • Missing weather data
  • No photos
  • Late submission
  • Missing subcontractor info
  • No issues section (even if none)
  • Inconsistent format

Do:

  • Be specific with quantities and locations
  • Document EVERYTHING
  • Take lots of photos
  • Submit on time, every time
  • Note even "no issues"
  • Use consistent format

  • Photo Documentation Standards
  • Pre-Task Planning Procedure
  • Incident Reporting Procedure
  • Weather Protocol

Software Integration

BLDR Pro Features:

  • Mobile daily report entry
  • Offline capability
  • Photo integration with GPS/timestamp
  • Manpower tracking
  • Weather auto-population
  • Email distribution
  • Historical report access
  • Report templates

Template provided by support.construction. Customize with your company information.