Skip to main content
Skip to main content

Productivity Loss & Disruption Claims

Document Type: Advanced Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Estimators, Claims Personnel
Complexity: Enterprise-level


Purposeโ€‹

Provide sophisticated methodologies for quantifying and proving productivity loss claims, including measured mile, industry studies, and total cost approaches.


Why Productivity Claims Are Difficultโ€‹

  • Causation is complex - Many factors affect productivity
  • Documentation is critical - Must track as work occurs
  • Burden of proof is high - Contractor must prove impact
  • Owners challenge aggressively - High-value, hard to verify
  • Methods have limitations - No perfect approach

Types of Productivity Lossโ€‹

1. Direct Impactโ€‹

Specific events causing immediate productivity loss:

  • Out-of-sequence work
  • Stacking of trades
  • Overtime inefficiency
  • Adverse weather
  • Site access restrictions

2. Cumulative Impactโ€‹

Aggregate effect of multiple changes:

  • Death by a thousand cuts
  • Ripple effects
  • Learning curve disruption
  • Management distraction

3. Accelerationโ€‹

Required to complete on time despite excusable delay:

  • Overtime premium
  • Additional crews
  • Shift work
  • Compressed schedule

Productivity Measurement Methodsโ€‹

Method 1: Measured Mile Analysisโ€‹

The Preferred Method When Possible

Concept:โ€‹

Compare productivity during impacted period to productivity during unimpacted period on same project.

Requirements:โ€‹

  • Same or similar work
  • Same crew (ideally)
  • Unimpacted baseline period
  • Detailed records

Calculation:โ€‹

Baseline Productivity (Unimpacted):
Units รท Hours = Units/Hour (or Hours/Unit)

Impacted Productivity:
Units รท Hours = Units/Hour

Loss Factor:
(Baseline - Impacted) รท Baseline = % Loss

Damages:
Impacted Hours ร— Loss % ร— Labor Rate = Lost Productivity $

Example:โ€‹

Electrical Conduit Installation:

Baseline Period (Months 1-3, unimpacted):
- 10,000 LF installed
- 2,000 labor hours
- Productivity: 5.0 LF/hour

Impacted Period (Months 4-8, stacking/changes):
- 15,000 LF installed
- 4,500 labor hours
- Productivity: 3.3 LF/hour

Loss:
(5.0 - 3.3) รท 5.0 = 34% productivity loss

Expected hours at baseline: 15,000 รท 5.0 = 3,000 hours
Actual hours: 4,500 hours
Lost hours: 1,500 hours

Damages at $75/hour: 1,500 ร— $75 = $112,500

Strengths:โ€‹

  • Project-specific data
  • Accounts for learning curve
  • Same crew/conditions
  • Most defensible

Limitations:โ€‹

  • Need unimpacted period
  • Sufficient data points
  • Work must be comparable

Method 2: Industry Studiesโ€‹

When Measured Mile Not Available

MCAA Study (Mechanical Contractors):โ€‹

Factors for various impact conditions

ConditionLoss Factor
Stacking of trades10-15%
Overtime (50+ hrs/wk)10-15%
Morale/attitude5-15%
Reassignment of manpower5-10%
Site access5-12%
Beneficial occupancy15-25%
Joint occupancy5-15%

NECA Study (Electrical Contractors):โ€‹

Similar factors for electrical trades

Leonard Study:โ€‹

Impact of changes on productivity

% Change OrdersProductivity Loss
0-10%Minimal
10-20%8-12%
20-30%12-20%
30%+20-30%+

Cautions:โ€‹

  • Not project-specific
  • Owners challenge applicability
  • Use as cross-check
  • Best combined with project data

Method 3: Total Cost Approachโ€‹

Last Resort Method

Concept:โ€‹

Claim difference between bid cost and actual cost.

Formula:โ€‹

Actual Cost - Bid Cost = Claimed Damages

Requirements (Courts require ALL):โ€‹

  1. Nature of work makes detailed cost proof impractical
  2. Bid was reasonable
  3. Actual costs are reasonable
  4. Contractor not responsible for cost increase

Weaknesses:โ€‹

  • Assumes bid was accurate
  • Doesn't prove causation
  • Doesn't separate contractor issues
  • Often rejected by tribunals

When Acceptable:โ€‹

  • Extremely complex impact
  • Records don't allow other methods
  • Clear owner causation
  • No contractor fault

Method 4: Modified Total Costโ€‹

Concept:โ€‹

Total cost approach with adjustments for known contractor issues.

Formula:โ€‹

Actual Cost 
- Bid Cost
- Known Contractor Issues
- Bid Errors
= Net Claimed Damages

More Defensible Than Pure Total Cost:โ€‹

  • Acknowledges imperfect bid
  • Removes contractor delays
  • Shows good faith

Cumulative Impact Claimsโ€‹

The "Ripple Effect":โ€‹

Multiple small changes create compounding impacts:

  • Each change disrupts workflow
  • Crews constantly remobilize
  • Management overwhelmed
  • Learning curve resets
  • Efficiency degrades project-wide

Quantification Approaches:โ€‹

1. Track Cumulative Hours:

  • Budget hours by activity
  • Actual hours by activity
  • Variance analysis
  • Correlation to change order volume

2. Leonard/Ibbs Study:

  • Correlates CO% to productivity loss
  • Academic basis
  • Challenged but used

3. Project-Specific Analysis:

  • Document each disruption
  • Estimate each impact
  • Sum total effects
  • Cross-check reasonableness

Documentation Requirementsโ€‹

Real-Time Tracking Critical:โ€‹

DocumentFrequencyData
Productivity reportsWeeklyUnits/hours by task
Daily reportsDailyCrew size, work performed, delays
Manpower logsDailyWorkers by trade, hours
Change order logOngoingCOs, PCOs, timing, impact
Disruption logAs occursEvents, impact, duration
Photo documentationDailyProgress, conditions

Disruption Log Format:โ€‹

================================================================
DISRUPTION EVENT LOG
================================================================

Date: ______________ Event #: _____________

Description: _______________________________________________
___________________________________________________________

Cause: ____________________________________________________

Impact:
- Work affected: __________________________________________
- Crew(s) impacted: _______________________________________
- Hours lost: _____________________________________________
- Estimated productivity loss: ______%

Supporting Documents:
โ˜ Daily report
โ˜ Photos
โ˜ Correspondence
โ˜ RFI/Submittal

Notice Provided: โ˜ Yes Date: __________ โ˜ No

Logged By: ________________________ Date: ________________

================================================================

Proving Causationโ€‹

Elements Required:โ€‹

  1. Owner action or inaction caused disruption
  2. Disruption caused productivity loss
  3. Loss is quantifiable
  4. Contractor did not cause loss

Causation Analysis:โ€‹

Event โ†’ Direct Impact โ†’ Productivity Loss โ†’ Damages

Example:
Stacking (Event)
โ†’ Trades in same area (Impact)
โ†’ 25% productivity loss (Measurement)
โ†’ $150,000 additional labor (Damages)

Acceleration Claimsโ€‹

Types:โ€‹

Directed Acceleration:

  • Owner directs faster completion
  • Usually documented
  • Straightforward claim

Constructive Acceleration:

  • Excusable delay occurs
  • Time extension requested
  • Time extension denied (or ignored)
  • Contractor directed to maintain schedule
  • Must accelerate to comply

Constructive Acceleration Elements:โ€‹

  1. Excusable delay occurred
  2. Timely notice and time extension request
  3. Request denied or not timely granted
  4. Order to maintain schedule
  5. Actual acceleration
  6. Acceleration costs incurred

Acceleration Costs:โ€‹

ItemDocumentation
Overtime premiumPayroll, time cards
Additional crewsCrew logs, payroll
Shift premiumPayroll
EquipmentEquipment logs
SupervisionTime records
Lost efficiencyProductivity analysis

Expert Requirementsโ€‹

For Significant Productivity Claims:โ€‹

Construction Expert:

  • Understands means and methods
  • Can identify impacts
  • Industry credibility

Forensic Accountant:

  • Cost analysis
  • Damage quantification
  • Financial documentation

Scheduling Expert:

  • If schedule impacts involved
  • Critical path analysis
  • Acceleration proof

  • Schedule Delay Analysis
  • Claims Procedures
  • Change Order Management
  • Daily Reporting

Referencesโ€‹

  • MCAA Bulletin No. T-14 (Change Orders/Productivity)
  • NECA Overtime and Productivity Study
  • Leonard "Effects of Change Orders on Productivity"
  • Ibbs, et al. "Quantitative Impacts of Change"
  • Schwartzkopf "Calculating Lost Labor Productivity"

Template provided by support.construction. Enterprise-level productivity analysis for sophisticated claims.