Punch List Management Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Superintendents, Subcontractors


Purpose

Establish a systematic process for creating, tracking, and completing punch list items to achieve project closeout and final payment.


What is a Punch List?

A punch list (also called a snag list or deficiency list) is a document listing work that does not conform to contract specifications, typically compiled near the end of a project.

When Punch Lists Occur

PhaseTypePurpose
Pre-Substantial CompletionContractor's ListInternal QC
Substantial Completion WalkOwner's ListFormal deficiencies
Pre-Final CompletionFinal WalkVerify completion

Punch List Process Overview

Internal Inspection → Contractor Punch List → 
Correction Period → Substantial Completion Walk →
Owner Punch List → Complete Items →
Verification Walk → Final Completion

Step-by-Step Process

Step 1: Internal Pre-Punch (2-4 Weeks Before S.C.)

Contractor's Own Inspection:

Conduct thorough inspection of ALL areas:

  • Every room/space
  • All systems operational
  • Finishes complete
  • Hardware functional
  • Specialty items installed

Create Internal Punch List:

  • Identify all deficiencies
  • Document location and description
  • Take photos
  • Assign to responsible party
  • Set completion deadlines

Goal: Fix all items BEFORE owner's walk


Step 2: Assign Items to Responsible Parties

Determination:

  • Self-performed work → Internal crews
  • Subcontracted work → Subcontractor
  • Unclear responsibility → Determine and assign

Notification to Subs:

  • Provide detailed punch list
  • Include location, description, photos
  • Set firm deadline
  • Note: Final payment withheld until complete

Step 3: Track Completion

Track in Punch List Log:

  • Item number
  • Location
  • Description
  • Responsible party
  • Date assigned
  • Target date
  • Completion date
  • Verified by

Daily/Weekly Review:

  • Items completed
  • Items outstanding
  • Blockers/issues
  • Schedule to completion

Step 4: Substantial Completion Walk

Preparation:

  • Internal punch 95%+ complete
  • Systems operational
  • Spaces accessible and clean
  • Temporary items removed

Attendees:

  • Owner/Owner's Rep
  • Architect
  • GC (PM and Super)
  • Key subcontractors (optional)

Process:

  1. Walk all areas systematically
  2. Document each deficiency
  3. Take photos
  4. Note location precisely
  5. Create formal punch list

After Walk:

  • Finalize punch list
  • Distribute to all parties
  • Set completion deadline

Step 5: Complete Owner's Punch Items

Priority Order:

  1. Life safety items (immediate)
  2. Functional items
  3. Cosmetic items

Process:

  1. Assign each item to responsible party
  2. Set completion date
  3. Track daily progress
  4. Document completion
  5. Request verification

Step 6: Verification and Close-Out

Item Verification:

  • Verify each item is complete
  • Take "after" photos
  • Sign off on completion

Re-Walk (if needed):

  • Schedule final verification walk
  • Owner confirms completion
  • Document any remaining items
  • Complete any additions

Final Punch:

  • All items complete
  • Documentation provided
  • Ready for final completion

Punch List Item Documentation

Required Information Per Item:

Item #: P-001
Location: Building A, Room 103, East Wall
Description: Paint touch-up required at outlet cover
Photo: [attached]
Responsible Party: ABC Painting
Date Identified: 02/01/2026
Target Date: 02/08/2026
Completed: ☐
Completion Date: ___________
Verified By: ___________

Location Precision

Be Specific: ❌ "Room 103 needs paint" ✅ "Room 103, east wall, 4 feet from NE corner, 36" AFF - paint scratch"

Use References:

  • Room numbers
  • Grid lines
  • Cardinal directions
  • Distance from fixed points
  • Height from floor

Punch List Template

================================================================
PUNCH LIST
================================================================

PROJECT: ________________________ DATE: ____________

BUILDING: _______________________ PHASE: ____________

AREA: __________________________

LIST TYPE: ☐ Contractor Internal ☐ Owner Walk ☐ Final

================================================================

| Item | Location | Description | Trade | Status | Complete |
|------|----------|-------------|-------|--------|----------|
| 001 | | | | | |
| 002 | | | | | |
| 003 | | | | | |
| 004 | | | | | |
| 005 | | | | | |

================================================================

STATUS KEY: O = Open, IP = In Progress, C = Complete, V = Verified

SUMMARY:
Total Items: _____
Complete: _____
In Progress: _____
Open: _____

PREPARED BY: _________________________ DATE: ____________

================================================================

Punch List by Trade Categories

Common Punch Items by Trade:

Drywall:

  • Nail pops
  • Cracks at corners
  • Unfinished joints
  • Damaged areas
  • Improperly finished corners

Painting:

  • Touch-ups needed
  • Missed areas
  • Drips/runs
  • Wrong color
  • Poor coverage

Flooring:

  • Loose tiles
  • Transition strips
  • Damaged areas
  • Gaps at walls
  • Carpet seams visible

Doors/Hardware:

  • Alignment issues
  • Hardware not working
  • Damaged finishes
  • Door not closing properly
  • Missing hardware

Ceilings:

  • Tiles damaged/missing
  • Grid alignment
  • Damaged areas
  • Penetrations not finished

Plumbing:

  • Fixtures not working
  • Leaks
  • Damaged fixtures
  • Missing accessories
  • Valve tags missing

HVAC:

  • Diffusers damaged
  • Thermostats not working
  • Grilles dirty
  • Controls not functioning
  • Balancing incomplete

Electrical:

  • Cover plates missing
  • Fixtures not working
  • Switches/outlets loose
  • Panel schedules incomplete
  • Labels missing

Subcontractor Punch Management

Sub Notification Letter

TO: [Subcontractor Name]
FROM: [GC Company]
DATE: [Date]
RE: Punch List Items - [Project Name]

The following punch list items have been identified for
your scope of work:

[List items with locations]

All items must be completed by [DATE].

Please coordinate site access with our superintendent.
Final payment will not be released until all items are
complete and verified.

Contact [Name] at [Phone] with questions.

Non-Response Protocol

If Sub Not Responding:

  1. Day 3: Phone call and email reminder
  2. Day 7: Formal written notice
  3. Day 10: Notice of backcharge intent
  4. Day 14+: Perform work, backcharge sub

Punch List Best Practices

DO:

✅ Start internal punch early (2-4 weeks before S.C.) ✅ Be thorough - check everything ✅ Use photos extensively ✅ Be specific in descriptions ✅ Assign immediately ✅ Track daily ✅ Verify completion personally ✅ Document everything

DON'T:

❌ Wait until owner's walk to start punch ❌ Accept vague descriptions ❌ Lose track of items ❌ Let subs delay ❌ Close items without verification ❌ Forget areas (mechanical rooms, roof, etc.)


Technology for Punch Lists

Mobile App Benefits:

  • Real-time updates
  • Photo documentation
  • GPS location tagging
  • Assignment and tracking
  • Status notifications
  • Report generation

BLDR Pro Features:

  • Create punch items in field
  • Photo markup tools
  • Assign to trades
  • Track completion status
  • Generate reports
  • Export for meetings

Punch List Metrics

Track:

  • Total items identified
  • Items completed per day
  • Items remaining
  • Days to completion
  • Items by trade
  • Items by location

Targets:

  • Internal punch: 90%+ complete before owner walk
  • Owner punch: Complete within 2 weeks
  • Completion rate: 10-20 items/day (varies by complexity)

  • Substantial Completion Procedure
  • Final Documentation Procedure
  • Subcontractor Management
  • Quality Control Procedure

Software Integration

BLDR Pro Features:

  • Mobile punch list creation
  • Photo documentation
  • Trade assignment
  • Status tracking
  • Report generation
  • Client sharing

Template provided by support.construction. Customize with your company information.