Punch List Management Procedure
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Superintendents, Subcontractors
Purpose
Establish a systematic process for creating, tracking, and completing punch list items to achieve project closeout and final payment.
What is a Punch List?
A punch list (also called a snag list or deficiency list) is a document listing work that does not conform to contract specifications, typically compiled near the end of a project.
When Punch Lists Occur
| Phase | Type | Purpose |
|---|---|---|
| Pre-Substantial Completion | Contractor's List | Internal QC |
| Substantial Completion Walk | Owner's List | Formal deficiencies |
| Pre-Final Completion | Final Walk | Verify completion |
Punch List Process Overview
Internal Inspection → Contractor Punch List →
Correction Period → Substantial Completion Walk →
Owner Punch List → Complete Items →
Verification Walk → Final Completion
Step-by-Step Process
Step 1: Internal Pre-Punch (2-4 Weeks Before S.C.)
Contractor's Own Inspection:
Conduct thorough inspection of ALL areas:
- Every room/space
- All systems operational
- Finishes complete
- Hardware functional
- Specialty items installed
Create Internal Punch List:
- Identify all deficiencies
- Document location and description
- Take photos
- Assign to responsible party
- Set completion deadlines
Goal: Fix all items BEFORE owner's walk
Step 2: Assign Items to Responsible Parties
Determination:
- Self-performed work → Internal crews
- Subcontracted work → Subcontractor
- Unclear responsibility → Determine and assign
Notification to Subs:
- Provide detailed punch list
- Include location, description, photos
- Set firm deadline
- Note: Final payment withheld until complete
Step 3: Track Completion
Track in Punch List Log:
- Item number
- Location
- Description
- Responsible party
- Date assigned
- Target date
- Completion date
- Verified by
Daily/Weekly Review:
- Items completed
- Items outstanding
- Blockers/issues
- Schedule to completion
Step 4: Substantial Completion Walk
Preparation:
- Internal punch 95%+ complete
- Systems operational
- Spaces accessible and clean
- Temporary items removed
Attendees:
- Owner/Owner's Rep
- Architect
- GC (PM and Super)
- Key subcontractors (optional)
Process:
- Walk all areas systematically
- Document each deficiency
- Take photos
- Note location precisely
- Create formal punch list
After Walk:
- Finalize punch list
- Distribute to all parties
- Set completion deadline
Step 5: Complete Owner's Punch Items
Priority Order:
- Life safety items (immediate)
- Functional items
- Cosmetic items
Process:
- Assign each item to responsible party
- Set completion date
- Track daily progress
- Document completion
- Request verification
Step 6: Verification and Close-Out
Item Verification:
- Verify each item is complete
- Take "after" photos
- Sign off on completion
Re-Walk (if needed):
- Schedule final verification walk
- Owner confirms completion
- Document any remaining items
- Complete any additions
Final Punch:
- All items complete
- Documentation provided
- Ready for final completion
Punch List Item Documentation
Required Information Per Item:
Item #: P-001
Location: Building A, Room 103, East Wall
Description: Paint touch-up required at outlet cover
Photo: [attached]
Responsible Party: ABC Painting
Date Identified: 02/01/2026
Target Date: 02/08/2026
Completed: ☐
Completion Date: ___________
Verified By: ___________
Location Precision
Be Specific: ❌ "Room 103 needs paint" ✅ "Room 103, east wall, 4 feet from NE corner, 36" AFF - paint scratch"
Use References:
- Room numbers
- Grid lines
- Cardinal directions
- Distance from fixed points
- Height from floor
Punch List Template
================================================================
PUNCH LIST
================================================================
PROJECT: ________________________ DATE: ____________
BUILDING: _______________________ PHASE: ____________
AREA: __________________________
LIST TYPE: ☐ Contractor Internal ☐ Owner Walk ☐ Final
================================================================
| Item | Location | Description | Trade | Status | Complete |
|------|----------|-------------|-------|--------|----------|
| 001 | | | | | |
| 002 | | | | | |
| 003 | | | | | |
| 004 | | | | | |
| 005 | | | | | |
================================================================
STATUS KEY: O = Open, IP = In Progress, C = Complete, V = Verified
SUMMARY:
Total Items: _____
Complete: _____
In Progress: _____
Open: _____
PREPARED BY: _________________________ DATE: ____________
================================================================
Punch List by Trade Categories
Common Punch Items by Trade:
Drywall:
- Nail pops
- Cracks at corners
- Unfinished joints
- Damaged areas
- Improperly finished corners
Painting:
- Touch-ups needed
- Missed areas
- Drips/runs
- Wrong color
- Poor coverage
Flooring:
- Loose tiles
- Transition strips
- Damaged areas
- Gaps at walls
- Carpet seams visible
Doors/Hardware:
- Alignment issues
- Hardware not working
- Damaged finishes
- Door not closing properly
- Missing hardware
Ceilings:
- Tiles damaged/missing
- Grid alignment
- Damaged areas
- Penetrations not finished
Plumbing:
- Fixtures not working
- Leaks
- Damaged fixtures
- Missing accessories
- Valve tags missing
HVAC:
- Diffusers damaged
- Thermostats not working
- Grilles dirty
- Controls not functioning
- Balancing incomplete
Electrical:
- Cover plates missing
- Fixtures not working
- Switches/outlets loose
- Panel schedules incomplete
- Labels missing
Subcontractor Punch Management
Sub Notification Letter
TO: [Subcontractor Name]
FROM: [GC Company]
DATE: [Date]
RE: Punch List Items - [Project Name]
The following punch list items have been identified for
your scope of work:
[List items with locations]
All items must be completed by [DATE].
Please coordinate site access with our superintendent.
Final payment will not be released until all items are
complete and verified.
Contact [Name] at [Phone] with questions.
Non-Response Protocol
If Sub Not Responding:
- Day 3: Phone call and email reminder
- Day 7: Formal written notice
- Day 10: Notice of backcharge intent
- Day 14+: Perform work, backcharge sub
Punch List Best Practices
DO:
✅ Start internal punch early (2-4 weeks before S.C.) ✅ Be thorough - check everything ✅ Use photos extensively ✅ Be specific in descriptions ✅ Assign immediately ✅ Track daily ✅ Verify completion personally ✅ Document everything
DON'T:
❌ Wait until owner's walk to start punch ❌ Accept vague descriptions ❌ Lose track of items ❌ Let subs delay ❌ Close items without verification ❌ Forget areas (mechanical rooms, roof, etc.)
Technology for Punch Lists
Mobile App Benefits:
- Real-time updates
- Photo documentation
- GPS location tagging
- Assignment and tracking
- Status notifications
- Report generation
BLDR Pro Features:
- Create punch items in field
- Photo markup tools
- Assign to trades
- Track completion status
- Generate reports
- Export for meetings
Punch List Metrics
Track:
- Total items identified
- Items completed per day
- Items remaining
- Days to completion
- Items by trade
- Items by location
Targets:
- Internal punch: 90%+ complete before owner walk
- Owner punch: Complete within 2 weeks
- Completion rate: 10-20 items/day (varies by complexity)
Related Documents
- Substantial Completion Procedure
- Final Documentation Procedure
- Subcontractor Management
- Quality Control Procedure
Software Integration
BLDR Pro Features:
- Mobile punch list creation
- Photo documentation
- Trade assignment
- Status tracking
- Report generation
- Client sharing
Template provided by support.construction. Customize with your company information.