Change Order Management Procedure
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Superintendents, Estimating
Purpose
Establish a consistent process for identifying, documenting, pricing, and managing change orders to protect company interests and maintain positive client relationships.
Change Order Types
| Type | Description | Typical Cause |
|---|---|---|
| Owner-Directed | Client requests additional work | Scope additions |
| Design Change | Architect/Engineer changes | Drawing revisions |
| Field Condition | Unexpected site conditions | Concealed conditions |
| Code Compliance | Required for code compliance | Inspector requirements |
| Value Engineering | Cost-saving alternatives | Contractor proposal |
| Time Extension | Schedule impact only | Delays outside contractor control |
Change Order Process Overview
Identification → Documentation → Pricing →
Submission → Negotiation → Approval → Execution
Step 1: Identification and Documentation
Recognize Change Order Conditions
STOP and document when:
- Owner requests additional work
- Drawings are revised (RFI response, ASI, bulletin)
- Field conditions differ from plans
- Inspector requires additional work
- Design error/omission discovered
- Subcontractor identifies changed work
Initial Documentation (Critical!)
Immediately document:
- Date and time condition identified
- Detailed description
- Location (specific)
- Reference to contract documents
- Photos (before any work)
- Witnesses/attendees
Notify in Writing:
- Send written notice to owner/architect
- Reference contract change order provisions
- Do NOT begin work until approved (unless emergency)
Potential Change Order (PCO) Log
Track all potential changes:
| PCO # | Date | Description | Est. Value | Status |
|---|---|---|---|---|
| PCO-001 | 1/15 | Added outlets per owner | $5,500 | Pending |
| PCO-002 | 1/18 | Rock encountered | TBD | Pricing |
Step 2: Change Order Request
Written Change Order Request
Submit to Owner/Architect:
CHANGE ORDER REQUEST
COR Number: COR-2026-001
Date: [Date]
Project: [Project Name]
Project Number: [Number]
Description of Changed Work:
[Detailed description of additional/changed work]
Reason for Change:
☐ Owner Request
☐ Design Change (RFI #___, ASI #___, Bulletin #___)
☐ Concealed Condition
☐ Code Requirement
☐ Other: ________________
Reference Documents:
- Contract Section: _______________
- Drawing Reference: _______________
- RFI/ASI Number: _______________
Cost Impact: $_____________ (estimate, formal pricing to follow)
Schedule Impact: _______ days
Requested By: _______________
Date: _______________
Step 3: Pricing
Pricing Requirements
Direct Costs:
- Labor (hours × rate)
- Materials (quantity × unit cost)
- Equipment (hours/days × rate)
- Subcontractor costs
Indirect Costs:
- Supervision
- Small tools
- Consumables
Markups (per contract):
- Overhead (typically 10-15%)
- Profit (typically 10%)
- Bond (if bonded)
Pricing Format
CHANGE ORDER PROPOSAL
COP Number: COP-2026-001
COR Reference: COR-2026-001
Date: [Date]
Project: [Project Name]
Description:
[Detailed scope description]
COST BREAKDOWN:
LABOR:
| Description | Hours | Rate | Total |
|-------------|-------|------|-------|
| Foreman | 8 | $65 | $520 |
| Journeyman | 16 | $55 | $880 |
| Labor | 24 | $40 | $960 |
LABOR SUBTOTAL: $2,360
MATERIALS:
| Description | Qty | Unit | Unit Cost | Total |
|-------------|-----|------|-----------|-------|
| [Material 1] | 100 | LF | $2.50 | $250 |
| [Material 2] | 50 | EA | $15.00 | $750 |
MATERIALS SUBTOTAL: $1,000
EQUIPMENT:
| Description | Qty | Rate | Total |
|-------------|-----|------|-------|
| Backhoe | 1 day | $450 | $450 |
EQUIPMENT SUBTOTAL: $450
SUBCONTRACTOR:
| Subcontractor | Scope | Amount |
|---------------|-------|--------|
| ABC Electric | Added circuits | $1,200 |
SUB SUBTOTAL: $1,200
DIRECT COST TOTAL: $5,010
MARKUPS:
Overhead (10%): $501
Profit (10%): $551
TOTAL CHANGE ORDER: $6,062
SCHEDULE IMPACT: [X] days extension requested
Supporting Documentation Attached:
☐ Labor breakdown
☐ Material quotes
☐ Sub quotes
☐ Drawings/sketches
☐ Photos
Subcontractor Change Orders
Process for Sub Changes:
- Sub submits PCO to GC
- PM reviews for validity
- Verify scope and pricing
- Add GC markup (per contract)
- Include in GC change order to owner
- Do NOT approve sub CO until owner approves
Step 4: Submission and Negotiation
Submit to Owner/Architect
Include:
- Change Order Proposal (detailed pricing)
- Supporting documentation
- Schedule impact analysis
- Drawings/sketches if needed
- Reference to contract provisions
Follow Up
Track response time:
- Per contract terms (typically 14-30 days)
- Send reminder if no response
- Document all communication
Negotiation
If owner disputes:
- Meet to discuss
- Be prepared to justify costs
- Review comparable work costs
- Consider value engineering
- Document negotiation results
- Do not agree to lose money
Step 5: Approval
Before Work Begins
Ideal: Written approval before starting changed work
Reality: Sometimes work must proceed. If so:
- Get verbal approval
- Document with confirming email
- Note "work proceeding at owner direction"
- Continue pursuing written approval
Change Order Execution
Standard Change Order Format:
CHANGE ORDER
Change Order Number: CO-001
Date: [Date]
Project: [Project Name]
Owner: [Owner Name]
Contractor: [Your Company]
DESCRIPTION OF CHANGE:
[Detailed description]
CONTRACT ADJUSTMENT:
Original Contract Sum: $_______________
Previous Change Orders: $_______________
This Change Order: $_______________
New Contract Sum: $_______________
SCHEDULE ADJUSTMENT:
Contract Time Previously Authorized: ___ days
Time Added This Change Order: ___ days
New Contract Time: ___ days
The above changes are approved and agreed to by:
OWNER:
Signature: _______________ Date: ___
Printed Name: _______________
Title: _______________
CONTRACTOR:
Signature: _______________ Date: ___
Printed Name: _______________
Title: _______________
ARCHITECT:
Signature: _______________ Date: ___
Printed Name: _______________
Title: _______________
Step 6: Execution and Tracking
After Approval
- Issue work authorization to field
- Notify affected subcontractors
- Update budget (add to job cost)
- Update schedule (if time granted)
- Update billing (add to SOV)
- Execute sub change orders
- Document completed work
Change Order Log
Maintain running log:
| CO # | Description | Amount | Status | Approved |
|---|---|---|---|---|
| CO-001 | Added outlets | $6,062 | Approved | 2/15/26 |
| CO-002 | Rock removal | $12,500 | Pending | - |
Critical Change Order Practices
DO:
✅ Document everything immediately
✅ Send written notice before proceeding
✅ Reference contract provisions
✅ Include detailed cost breakdown
✅ Get written approval before work
✅ Track all changes in log
✅ Update budget and billing
DON'T:
❌ Perform changed work without notice
❌ Accept verbal-only approval for large changes
❌ Wait to document conditions
❌ Under-price to avoid conflict
❌ Forget to include time extension
❌ Bundle multiple changes into one
Time Impact Analysis
When Schedule Impact Exists
-
Document delay cause
- What triggered the delay
- Critical path impact
-
Quantify impact
- Days of delay
- Affected activities
- Ripple effects
-
Request time extension
- With change order if cost involved
- Separate request if no cost impact
Time Extension Considerations
- Weather delays (check contract)
- Owner-caused delays
- Design delays
- Force majeure
- Concurrent delays
Related Documents
- Change Order Request Template
- Change Order Proposal Template
- Change Order Log
- Time Impact Analysis Template
- Subcontractor Change Order Process
Software Integration
BLDR Pro Features:
- PCO tracking
- Photo documentation
- Cost tracking
- Change order history
- Budget integration
- Mobile field access