Schedule Delay Analysis Methods
Document Type: Advanced Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Schedulers, Claims Personnel
Complexity: Enterprise-level
Purpose
Provide sophisticated schedule delay analysis methodologies aligned with AACE International recommended practices for use in claims, disputes, and project controls.
Why This Matters
For enterprise contractors:
- Delay claims can be worth millions
- Proper methodology determines success
- Courts and arbitrators expect sophistication
- Owners increasingly have sophisticated schedulers
- Insufficient analysis = denied claims
Delay Analysis Methods Overview
| Method | Complexity | Prospective/ Retrospective | Best Used For |
|---|---|---|---|
| As-Planned vs. As-Built | Low | Retrospective | Simple delays, low value |
| Impacted As-Planned | Medium | Prospective | During project, time extensions |
| Collapsed As-Built (But-For) | High | Retrospective | Claims, litigation |
| Time Impact Analysis (TIA) | High | Both | Gold standard for claims |
| Windows Analysis | High | Retrospective | Complex, multiple delays |
AACE Recommended Practices
RP 29R-03: Forensic Schedule Analysis
Key Principles:
- Use contemporaneous schedules
- Document delay events
- Apply appropriate methodology
- Quantify critical path impact
- Address concurrent delays
- Validate with actual performance
Method 1: As-Planned vs. As-Built
Overview:
Compare original schedule to actual completion dates.
Process:
- Identify planned start/finish dates
- Document actual start/finish dates
- Calculate variance
- Identify causes
Limitations:
- Doesn't prove causation
- Doesn't address concurrent delays
- May not reflect schedule updates
- Generally insufficient for litigation
When to Use:
- Low-value claims
- Simple, single-cause delays
- Initial screening
Method 2: Impacted As-Planned
Overview:
Add delay events to as-planned schedule to show impact.
Process:
- Start with baseline schedule
- Insert delay activities
- Re-calculate critical path
- Measure project delay
Strengths:
- Shows theoretical impact
- Useful for time extension requests
- Relatively straightforward
Limitations:
- Doesn't reflect actual performance
- Baseline may not have been realistic
- Assumes logic intact
When to Use:
- Prospective analysis during project
- Time extension requests
- What-if scenarios
Method 3: Collapsed As-Built (But-For)
Overview:
Remove delay events from as-built schedule to show "but-for" completion.
Process:
- Create as-built schedule
- Remove owner/excusable delay activities
- Re-calculate to show "but-for" completion
- Difference = compensable delay
Strengths:
- Based on actual performance
- Shows what would have happened
- Accepted by many tribunals
Limitations:
- Requires accurate as-built
- Subtractive approach challenged
- Concurrent delay issues
When to Use:
- Retrospective claims
- After project completion
- When as-built is well-documented
Method 4: Time Impact Analysis (TIA)
Overview:
Insert delay events into schedule at time of occurrence, measure impact contemporaneously.
Process:
- Identify delay event
- Use schedule update just before event
- Insert delay activity with logic ties
- Calculate impact to completion
- Repeat for each event
The Gold Standard:
- AACE preferred method
- Most defensible
- Addresses concurrent delays
- Matches contemporaneous records
Requirements:
- Regular schedule updates
- Documented delay events
- Logic ties understood
- Skilled scheduler
When to Use:
- Complex delays
- High-value claims
- Litigation/arbitration
- Multiple delay causes
Method 5: Windows Analysis
Overview:
Divide project into time "windows" and analyze each period.
Process:
- Divide project into periods (monthly, milestone-based)
- For each window:
- Identify critical path
- Measure delay
- Attribute to responsible party
- Sum delays across windows
- Net excusable vs. non-excusable
Strengths:
- Handles concurrent delays well
- Shows delay development over time
- Matches monthly reporting
Limitations:
- Very labor intensive
- Requires excellent records
- Complex presentation
When to Use:
- Complex projects with many delays
- Concurrent delay situations
- Large claims requiring detailed analysis
Critical Path Analysis
Identifying Critical Path:
Total Float = 0 → Activity is critical Total Float > 0 → Activity has flexibility
Critical Path Shifts:
- Delays to critical activities extend project
- Non-critical delays may become critical
- As-built critical path may differ from planned
Documentation Required:
- Baseline schedule with critical path
- Updates showing critical path changes
- Float consumption tracking
- Near-critical path monitoring
Concurrent Delay
Definition:
Two or more delays occurring at the same time, both impacting completion.
Types:
| Type | Owner Delay | Contractor Delay | Result |
|---|---|---|---|
| True concurrent | Critical | Critical | Time only, no costs |
| Sequential | First | Second | Apportion |
| Dominant | Minor | Major | Contractor bears |
Handling Concurrent Delay:
Approaches vary by jurisdiction:
- Apportionment (some courts)
- Malmaison approach (UK - time but no costs)
- First-in-line (whoever caused first delay)
- Contractor bears all (strict approach)
Best Practice:
- Document meticulously
- Separate analysis for each delay
- Identify dominant cause where possible
- Prepare for apportionment
Schedule Analysis Checklist
================================================================
DELAY ANALYSIS PREPARATION CHECKLIST
================================================================
Project: ___________________________________________________
Claim Period: ______________________________________________
================================================================
SCHEDULE DOCUMENTATION:
☐ Baseline schedule (accepted)
☐ All schedule updates (monthly)
☐ As-built schedule
☐ Schedule narratives
☐ Recovery schedules (if any)
☐ Acceleration plans (if any)
DELAY DOCUMENTATION:
☐ Delay events log (with dates)
☐ Notice letters sent
☐ RFIs related to delays
☐ Weather records
☐ Force majeure documentation
☐ Owner/architect correspondence
CONTEMPORANEOUS RECORDS:
☐ Daily reports
☐ Meeting minutes
☐ Progress photos
☐ Manpower logs
☐ Equipment logs
ANALYSIS ELEMENTS:
☐ Critical path identified (each period)
☐ Float consumption tracked
☐ Concurrent delays addressed
☐ Methodology documented
☐ Cause-and-effect established
================================================================
Delay Analysis Report Outline
1. Executive Summary
- Total delay claimed
- Responsible party allocation
- Methodology used
2. Project Background
- Contract scope and schedule
- Key milestones
- Baseline schedule overview
3. Methodology
- Analysis method selected
- Why appropriate
- Data sources
- Assumptions
4. Chronology of Events
- Timeline of delay events
- Impact of each event
- Critical path analysis
5. Delay Analysis
- Detailed calculations
- Schedule excerpts
- Float analysis
- Concurrent delay treatment
6. Conclusion
- Days of delay by cause
- Compensable vs. excusable
- Summary schedule impact
7. Exhibits
- Schedules
- Correspondence
- Calculations
- Supporting documents
Common Delay Analysis Errors
| Error | Problem | Prevention |
|---|---|---|
| No critical path analysis | Can't prove project delay | Always analyze CP |
| Ignoring float | Over-claims | Track float consumption |
| Using wrong baseline | Foundational error | Verify accepted schedule |
| Ignoring concurrent delays | Claim rejected | Address head-on |
| After-the-fact schedules | Not contemporaneous | Use real updates |
| Missing documentation | Can't support claim | Document in real-time |
Expert Requirements
For Complex Claims, Consider:
Scheduling Expert:
- CPM scheduling experience
- Construction background
- Forensic analysis experience
- Credibility with tribunals
Expert Report Should Include:
- Qualifications
- Materials reviewed
- Methodology
- Opinions and basis
- Supporting exhibits
Related Documents
- Schedule Management Procedure
- Claims Procedures
- Change Order Management
- Daily Reporting
References
- AACE International RP 29R-03 (Forensic Schedule Analysis)
- AACE International RP 52R-06 (Time Impact Analysis)
- SCL Delay and Disruption Protocol (UK)
- Long International papers on delay analysis
Template provided by support.construction. Enterprise-level schedule analysis for sophisticated claims.