Mechanics Lien Filing Procedure (California)
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: AR Team, Project Managers, Legal, Executives
Purposeโ
Establish the process for filing a mechanics lien when payment is not received, to protect the company's legal right to recover payment for work performed.
โ ๏ธ CRITICAL DEADLINESโ
| Action | California Deadline | Consequence of Missing |
|---|---|---|
| Preliminary Notice | 20 days from first work | Lien limited to 20 days before notice |
| Mechanics Lien | 90 days from completion | LOSE ALL LIEN RIGHTS |
| Lawsuit to Enforce | 90 days from lien recording | Lien becomes unenforceable |
These deadlines are ABSOLUTE. There are NO extensions.
When to Consider Filing a Lienโ
Lien Filing Triggersโ
- Payment 60+ days past due
- Owner/GC non-responsive to collection efforts
- Demand letters ignored
- No reasonable payment plan offered
- Project nearing completion (deadline approaching)
- Significant amount at stake ($10,000+)
Before Filing - Verify:โ
- Preliminary notice was sent timely
- Work was actually performed
- Payment is legitimately owed
- No valid dispute on the work
- All billing documentation complete
- Deadline calculation is correct
Calculating the 90-Day Deadlineโ
What is "Completion"?โ
For Direct Contractors (GC to Owner):
- Completion of the entire project
- Recording of Notice of Completion (if recorded)
- Cessation of labor for continuous period
For Subcontractors/Suppliers:
- Completion of YOUR work (not entire project)
- Last day you furnished labor or materials
- Does NOT include warranty or punch list work
If Notice of Completion is Recordedโ
| Claimant Type | Deadline |
|---|---|
| Direct Contractor | 60 days from recording |
| Subcontractor | 30 days from recording |
| Material Supplier | 30 days from recording |
If NO Notice of Completionโ
All claimants: 90 days from actual completion
Step-by-Step Lien Filing Processโ
Step 1: Decision to File (Day 1)โ
Internal Review Meeting:
- AR Manager
- Project Manager
- Executive (for amounts over $50,000)
- Legal counsel (recommended)
Review:
- Amount owed and documentation
- Preliminary notice proof
- Deadline calculation
- Relationship considerations
- Collection efforts to date
Decision: Approve or reject lien filing
Step 2: Prepare Mechanics Lien Documentโ
Required Content (California Civil Code ยง 8416):
-
Claimant Information
- Name and address
- Type of claimant (contractor, sub, supplier)
-
Property Description
- Street address
- Legal description (from title report or assessor)
-
Owner Information
- Name of owner (or reputed owner)
- Address
-
Direct Contractor Information (if you're a sub)
- Name and address of GC
-
Work Description
- General statement of work furnished
- Labor, services, equipment, or materials
-
Amount of Claim
- Total amount claimed (can include interest if contractual)
-
Verification
- Signed under penalty of perjury
- Must be signed by claimant or authorized agent
Step 3: Record the Lienโ
Where to Record: County Recorder's Office in the county where the property is located
How to Record:
- Bring original lien document
- Pay recording fee ($15-50 typically)
- Obtain certified copy with recording information
Recording Information Captured:
- Document number
- Recording date and time
- Book and page (if applicable)
Step 4: Serve Copy of Recorded Lienโ
Must Serve Within 15 Days of Recording:
| Recipient | Required |
|---|---|
| Property Owner | Yes |
| Direct Contractor (if sub/supplier) | Yes |
| Construction Lender (if any) | Recommended |
Service Methods:
- Personal delivery
- Certified mail, return receipt
- Registered mail
Proof of Service: Complete and retain proof of service affidavit
Step 5: Enforce the Lien (File Lawsuit)โ
CRITICAL: You must file a lawsuit to foreclose the lien within 90 days of recording.
If No Lawsuit Filed:
- Lien becomes unenforceable
- You lose foreclosure rights
- Lien can be expunged from title
Lawsuit Considerations:
- Hire construction attorney
- Court filing fees ($400-500+)
- Time and legal costs
- Potential for settlement before trial
Mechanics Lien Form (California)โ
RECORDING REQUESTED BY:
[Your Company Name]
WHEN RECORDED MAIL TO:
[Your Company Name]
[Your Address]
[City, State ZIP]
SPACE ABOVE THIS LINE FOR RECORDER'S USE
================================================================
MECHANICS LIEN
(California Civil Code Section 8400 et seq.)
NOTICE IS HEREBY GIVEN that:
1. The undersigned claimant claims a mechanics lien upon the
real property hereinafter described.
2. CLAIMANT INFORMATION:
Name: [Your Company Name]
Address: [Your Street Address]
[City, State ZIP]
3. The claimant is: [check one]
โ A direct contractor
โ A subcontractor
โ A material supplier
โ An equipment lessor
โ A laborer
4. NAME OF OWNER OR REPUTED OWNER:
[Property Owner Name]
5. PROPERTY DESCRIPTION:
Street Address: [Property Address]
Legal Description: [Legal description from title report]
APN: [Assessor's Parcel Number]
6. NAME OF DIRECT CONTRACTOR:
[General Contractor Name] (if claimant is sub/supplier)
[N/A if claimant is direct contractor]
7. GENERAL STATEMENT OF WORK:
The claimant furnished the following labor, services,
equipment, or materials for the work of improvement:
[Description of work - e.g., "Electrical installation
including rough-in, finish electrical, and fixtures for
new commercial building construction"]
8. AMOUNT OF LIEN CLAIM:
The amount of the demand, after deducting all just credits
and offsets, is: $[Amount]
9. The claimant claims a lien on the above-described property
and improvements thereon, and on so much land as may be
required for the convenient use thereof.
VERIFICATION
I, the undersigned, say: I am the [title] of the claimant
herein; I have read the foregoing Mechanics Lien and know the
contents thereof, and I certify that the same is true of my
own knowledge.
I declare under penalty of perjury under the laws of the State
of California that the foregoing is true and correct.
Executed on [Date] at [City], California.
_________________________________
[Printed Name]
[Title]
[Company Name]
================================================================
After Lien is Recordedโ
Immediate Actionsโ
- Calendar 90-day lawsuit deadline
- Send copies to owner and GC
- Notify your attorney
- Continue collection efforts
- Document all communication
Potential Outcomesโ
1. Payment in Full
- Receive payment
- Execute lien release
- Record release with county
2. Settlement/Partial Payment
- Negotiate resolution
- Execute partial release if appropriate
- Document agreement
3. Lien Bond
- Owner may post bond to remove lien from property
- Lien transfers to bond
- You still have claim against bond
4. Foreclosure Lawsuit
- File within 90 days
- Prosecute claim through court
- Potential sale of property to satisfy lien
Lien Releaseโ
When Payment Received:
You MUST provide a lien release when paid. Use the statutory forms:
- Unconditional Waiver and Release (after payment clears)
Recording the Release:
- Prepare release document
- Record with county recorder
- Provide copy to owner
Lien Filing Checklistโ
Before Filingโ
- Amount owed verified
- Preliminary notice on file with proof
- Deadline calculated correctly
- Owner/property information verified
- Legal description obtained
- Management approval obtained
- Attorney consulted (recommended)
Filingโ
- Lien document prepared
- Signed under penalty of perjury
- Recorded with county recorder
- Certified copy obtained
- Recording fee paid
After Filingโ
- Copy served on owner (within 15 days)
- Copy served on GC (within 15 days)
- Proof of service retained
- 90-day lawsuit deadline calendared
- Attorney engaged for enforcement
- Continue collection efforts
Common Lien Mistakesโ
โ Avoid These:
- Missing 90-day deadline
- Wrong property legal description
- Filing without valid preliminary notice
- Wrong claimant type identified
- Math errors in amount
- Failing to serve copies
- Failing to file lawsuit within 90 days
โ Best Practices:
- File early (don't wait until day 89)
- Double-check legal description
- Have attorney review before recording
- Keep meticulous records
- Calendar ALL deadlines
Related Documentsโ
- Preliminary Notice Procedure
- Lien Waiver Management
- Collections Procedure
- California Mechanics Lien Form
- Lien Release Form
Legal Referenceโ
California Civil Code Sections:
- ยง 8400-8494 (Mechanics Lien provisions)
- ยง 8416 (Lien content requirements)
- ยง 8460 (Time for recording)
- ยง 8412 (Amount of lien)
This document provides general information. Consult with legal counsel before filing any lien.
Template provided by support.construction. Verify current law with legal counsel.