Skip to main content
Skip to main content

Mechanics Lien Filing Procedure (California)

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: AR Team, Project Managers, Legal, Executives


Purposeโ€‹

Establish the process for filing a mechanics lien when payment is not received, to protect the company's legal right to recover payment for work performed.


โš ๏ธ CRITICAL DEADLINESโ€‹

ActionCalifornia DeadlineConsequence of Missing
Preliminary Notice20 days from first workLien limited to 20 days before notice
Mechanics Lien90 days from completionLOSE ALL LIEN RIGHTS
Lawsuit to Enforce90 days from lien recordingLien becomes unenforceable

These deadlines are ABSOLUTE. There are NO extensions.


When to Consider Filing a Lienโ€‹

Lien Filing Triggersโ€‹

  • Payment 60+ days past due
  • Owner/GC non-responsive to collection efforts
  • Demand letters ignored
  • No reasonable payment plan offered
  • Project nearing completion (deadline approaching)
  • Significant amount at stake ($10,000+)

Before Filing - Verify:โ€‹

  • Preliminary notice was sent timely
  • Work was actually performed
  • Payment is legitimately owed
  • No valid dispute on the work
  • All billing documentation complete
  • Deadline calculation is correct

Calculating the 90-Day Deadlineโ€‹

What is "Completion"?โ€‹

For Direct Contractors (GC to Owner):

  • Completion of the entire project
  • Recording of Notice of Completion (if recorded)
  • Cessation of labor for continuous period

For Subcontractors/Suppliers:

  • Completion of YOUR work (not entire project)
  • Last day you furnished labor or materials
  • Does NOT include warranty or punch list work

If Notice of Completion is Recordedโ€‹

Claimant TypeDeadline
Direct Contractor60 days from recording
Subcontractor30 days from recording
Material Supplier30 days from recording

If NO Notice of Completionโ€‹

All claimants: 90 days from actual completion


Step-by-Step Lien Filing Processโ€‹

Step 1: Decision to File (Day 1)โ€‹

Internal Review Meeting:

  • AR Manager
  • Project Manager
  • Executive (for amounts over $50,000)
  • Legal counsel (recommended)

Review:

  • Amount owed and documentation
  • Preliminary notice proof
  • Deadline calculation
  • Relationship considerations
  • Collection efforts to date

Decision: Approve or reject lien filing


Step 2: Prepare Mechanics Lien Documentโ€‹

Required Content (California Civil Code ยง 8416):

  1. Claimant Information

    • Name and address
    • Type of claimant (contractor, sub, supplier)
  2. Property Description

    • Street address
    • Legal description (from title report or assessor)
  3. Owner Information

    • Name of owner (or reputed owner)
    • Address
  4. Direct Contractor Information (if you're a sub)

    • Name and address of GC
  5. Work Description

    • General statement of work furnished
    • Labor, services, equipment, or materials
  6. Amount of Claim

    • Total amount claimed (can include interest if contractual)
  7. Verification

    • Signed under penalty of perjury
    • Must be signed by claimant or authorized agent

Step 3: Record the Lienโ€‹

Where to Record: County Recorder's Office in the county where the property is located

How to Record:

  1. Bring original lien document
  2. Pay recording fee ($15-50 typically)
  3. Obtain certified copy with recording information

Recording Information Captured:

  • Document number
  • Recording date and time
  • Book and page (if applicable)

Step 4: Serve Copy of Recorded Lienโ€‹

Must Serve Within 15 Days of Recording:

RecipientRequired
Property OwnerYes
Direct Contractor (if sub/supplier)Yes
Construction Lender (if any)Recommended

Service Methods:

  • Personal delivery
  • Certified mail, return receipt
  • Registered mail

Proof of Service: Complete and retain proof of service affidavit


Step 5: Enforce the Lien (File Lawsuit)โ€‹

CRITICAL: You must file a lawsuit to foreclose the lien within 90 days of recording.

If No Lawsuit Filed:

  • Lien becomes unenforceable
  • You lose foreclosure rights
  • Lien can be expunged from title

Lawsuit Considerations:

  • Hire construction attorney
  • Court filing fees ($400-500+)
  • Time and legal costs
  • Potential for settlement before trial

Mechanics Lien Form (California)โ€‹

RECORDING REQUESTED BY:
[Your Company Name]

WHEN RECORDED MAIL TO:
[Your Company Name]
[Your Address]
[City, State ZIP]

SPACE ABOVE THIS LINE FOR RECORDER'S USE
================================================================

MECHANICS LIEN
(California Civil Code Section 8400 et seq.)

NOTICE IS HEREBY GIVEN that:

1. The undersigned claimant claims a mechanics lien upon the
real property hereinafter described.

2. CLAIMANT INFORMATION:
Name: [Your Company Name]
Address: [Your Street Address]
[City, State ZIP]

3. The claimant is: [check one]
โ˜ A direct contractor
โ˜ A subcontractor
โ˜ A material supplier
โ˜ An equipment lessor
โ˜ A laborer

4. NAME OF OWNER OR REPUTED OWNER:
[Property Owner Name]

5. PROPERTY DESCRIPTION:
Street Address: [Property Address]
Legal Description: [Legal description from title report]

APN: [Assessor's Parcel Number]

6. NAME OF DIRECT CONTRACTOR:
[General Contractor Name] (if claimant is sub/supplier)
[N/A if claimant is direct contractor]

7. GENERAL STATEMENT OF WORK:
The claimant furnished the following labor, services,
equipment, or materials for the work of improvement:

[Description of work - e.g., "Electrical installation
including rough-in, finish electrical, and fixtures for
new commercial building construction"]

8. AMOUNT OF LIEN CLAIM:
The amount of the demand, after deducting all just credits
and offsets, is: $[Amount]

9. The claimant claims a lien on the above-described property
and improvements thereon, and on so much land as may be
required for the convenient use thereof.

VERIFICATION

I, the undersigned, say: I am the [title] of the claimant
herein; I have read the foregoing Mechanics Lien and know the
contents thereof, and I certify that the same is true of my
own knowledge.

I declare under penalty of perjury under the laws of the State
of California that the foregoing is true and correct.

Executed on [Date] at [City], California.

_________________________________
[Printed Name]
[Title]
[Company Name]

================================================================

After Lien is Recordedโ€‹

Immediate Actionsโ€‹

  1. Calendar 90-day lawsuit deadline
  2. Send copies to owner and GC
  3. Notify your attorney
  4. Continue collection efforts
  5. Document all communication

Potential Outcomesโ€‹

1. Payment in Full

  • Receive payment
  • Execute lien release
  • Record release with county

2. Settlement/Partial Payment

  • Negotiate resolution
  • Execute partial release if appropriate
  • Document agreement

3. Lien Bond

  • Owner may post bond to remove lien from property
  • Lien transfers to bond
  • You still have claim against bond

4. Foreclosure Lawsuit

  • File within 90 days
  • Prosecute claim through court
  • Potential sale of property to satisfy lien

Lien Releaseโ€‹

When Payment Received:

You MUST provide a lien release when paid. Use the statutory forms:

  • Unconditional Waiver and Release (after payment clears)

Recording the Release:

  • Prepare release document
  • Record with county recorder
  • Provide copy to owner

Lien Filing Checklistโ€‹

Before Filingโ€‹

  • Amount owed verified
  • Preliminary notice on file with proof
  • Deadline calculated correctly
  • Owner/property information verified
  • Legal description obtained
  • Management approval obtained
  • Attorney consulted (recommended)

Filingโ€‹

  • Lien document prepared
  • Signed under penalty of perjury
  • Recorded with county recorder
  • Certified copy obtained
  • Recording fee paid

After Filingโ€‹

  • Copy served on owner (within 15 days)
  • Copy served on GC (within 15 days)
  • Proof of service retained
  • 90-day lawsuit deadline calendared
  • Attorney engaged for enforcement
  • Continue collection efforts

Common Lien Mistakesโ€‹

โŒ Avoid These:

  • Missing 90-day deadline
  • Wrong property legal description
  • Filing without valid preliminary notice
  • Wrong claimant type identified
  • Math errors in amount
  • Failing to serve copies
  • Failing to file lawsuit within 90 days

โœ… Best Practices:

  • File early (don't wait until day 89)
  • Double-check legal description
  • Have attorney review before recording
  • Keep meticulous records
  • Calendar ALL deadlines

  • Preliminary Notice Procedure
  • Lien Waiver Management
  • Collections Procedure
  • California Mechanics Lien Form
  • Lien Release Form

California Civil Code Sections:

  • ยง 8400-8494 (Mechanics Lien provisions)
  • ยง 8416 (Lien content requirements)
  • ยง 8460 (Time for recording)
  • ยง 8412 (Amount of lien)

This document provides general information. Consult with legal counsel before filing any lien.


Template provided by support.construction. Verify current law with legal counsel.