Contract Risk Assessment Procedures

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Estimators, Project Managers, Executives


Purpose​

Establish procedures for assessing contract risk before bid submission and during negotiations to protect the company from unfavorable terms.


Why Contract Risk Assessment Matters​

Construction Contract Reality:​

  • Contracts allocate risk between parties
  • Unfavorable terms can eliminate profit
  • Some risks are uninsurable
  • Legal fees from disputes are significant
  • Bad contracts can threaten company survival

Risk Assessment Benefits:​

  • Avoid unacceptable risk
  • Price risk appropriately
  • Negotiate better terms
  • Protect the company
  • Informed go/no-go decisions

Contract Review Process​

Review Stages:​

StageWho ReviewsFocus
Bid stageEstimator + PMKey risk terms
Pre-awardLegal + ManagementFull contract
ExecutionAuthorized signatoryFinal terms

Risk Assessment Checklist​

Contract Risk Review:​

================================================================
CONTRACT RISK ASSESSMENT
================================================================

Project: _______________________
Client: _______________________
Contract value: $_________________
Reviewed by: _______________________
Date: _______________________

================================================================

SECTION 1: SCOPE RISK

☐ Scope clearly defined
☐ Drawings/specs adequate
☐ Site conditions addressed
☐ Allowances appropriate
☐ Exclusions clear

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 2: SCHEDULE RISK

Substantial completion: _______________________
Final completion: _______________________
Duration: _____ days

☐ Schedule is achievable
☐ Weather days adequate
☐ Owner delay provisions fair
☐ Acceleration provisions reasonable
☐ Milestone penalties assessed

Liquidated damages: $_______ /day
Exposure at 30 days late: $_______

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 3: PAYMENT RISK

Payment terms: Net _____ days
Retainage: _____%
Retainage release: _______________________

☐ Payment terms acceptable
☐ Pay-when-paid vs. pay-if-paid clear
☐ Retainage reasonable
☐ Lien rights preserved
☐ Change order payment terms defined
☐ Invoice requirements clear

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 4: CHANGE ORDER RISK

☐ Change order process defined
☐ Pricing markup defined
☐ Disputed work provisions
☐ Constructive change provisions
☐ Time extension process clear

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 5: INDEMNIFICATION

☐ Indemnification is mutual
☐ Limited to negligent acts
☐ No broad form indemnity
☐ Insurable exposures only
☐ Defense obligations clear

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 6: INSURANCE REQUIREMENTS

☐ GL limits achievable: $_______ / $_______
☐ Auto limits achievable: $_______
☐ Umbrella limits achievable: $_______
☐ Professional liability required: ☐ Yes ☐ No
☐ Pollution liability required: ☐ Yes ☐ No
☐ Builder's risk addressed
☐ Waiver of subrogation required
☐ Additional insured required
☐ Primary/non-contributory required

Additional premium cost: $_______

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 7: WARRANTY/GUARANTY

Standard warranty: _____ years
Extended warranty: _____ years
Workmanship warranty: _____ years

☐ Warranty terms standard
☐ No performance guarantees
☐ No consequential damages waiver
☐ Latent defect provisions reasonable

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 8: TERMINATION

☐ Termination for convenience provisions fair
☐ Termination for cause provisions fair
☐ Cure period adequate
☐ Payment on termination defined

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 9: DISPUTE RESOLUTION

☐ Dispute process defined
☐ Mediation before litigation
☐ Arbitration vs. litigation clear
☐ Venue acceptable
☐ Attorney fees provision fair
☐ Statute of limitations addressed

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

----------------------------------------------------------------

SECTION 10: OTHER PROVISIONS

☐ No-damage-for-delay clause? (RISK)
☐ Flow-down provisions reviewed
☐ Consequential damages waived (mutual)
☐ Limitation of liability?
☐ Force majeure provisions adequate
☐ Assignment restrictions reasonable

Risk level: ☐ Low ☐ Medium ☐ High

Concerns:
___________________________________________________________

================================================================

OVERALL RISK ASSESSMENT:

| Category | Risk Level | Impact |
|----------|------------|--------|
| Scope | | |
| Schedule | | |
| Payment | | |
| Change orders | | |
| Indemnification | | |
| Insurance | | |
| Warranty | | |
| Termination | | |
| Disputes | | |
| Other | | |

OVERALL RISK: ☐ Low ☐ Medium ☐ High ☐ Unacceptable

================================================================

High-Risk Contract Terms​

Red Flags to Watch:​

Red FlagRiskResponse
Broad form indemnificationUninsurable liabilityNegotiate to negligence-based
No-damage-for-delayNo recovery for owner delaysNegotiate exception or price
Pay-if-paidMay not get paidUnderstand and price
Consequential damagesUnlimited exposureNegotiate mutual waiver
One-sided terminationArbitrary terminationNegotiate cure period
Unlimited warrantyPerpetual liabilityNegotiate standard term
Attorney fees to owner onlyLopsided disputesNegotiate mutual provision
Waiver of lien rightsLoss of securityDo not waive
Performance guaranteesBeyond controlNegotiate to best efforts
Automatic assignmentForced to work for unknownNegotiate consent right

Risk Pricing​

Pricing Contract Risk:​

================================================================
RISK PRICING WORKSHEET
================================================================

Project: _______________________

================================================================

QUANTIFIABLE RISKS:

| Risk Item | Probability | Impact | Expected Value |
|-----------|-------------|--------|----------------|
| Schedule LD exposure | ___% | $ | $ |
| Additional insurance | 100% | $ | $ |
| Extended warranty | ___% | $ | $ |
| Unfavorable payment terms | ___% | $ | $ |
| Scope gaps | ___% | $ | $ |

Total quantifiable risk: $_________________

----------------------------------------------------------------

CONTINGENCY FOR UNQUANTIFIABLE RISKS:

Contract risk level: ☐ Low (1%) ☐ Medium (2-3%) ☐ High (4-5%)

Base bid: $_________________
Risk contingency: _____% = $_________________

----------------------------------------------------------------

RISK-ADJUSTED BID:

Base bid: $_________________
+ Quantifiable risk: $_________________
+ Risk contingency: $_________________
= Risk-adjusted bid: $_________________

================================================================

Negotiation Strategy​

Terms to Negotiate:​

================================================================
CONTRACT NEGOTIATION PRIORITIES
================================================================

Project: _______________________

================================================================

MUST CHANGE (Deal breakers if not modified):

1. Issue: _______________________
Current language: _______________________
Proposed change: _______________________
Fallback: _______________________

2. Issue: _______________________
Current language: _______________________
Proposed change: _______________________
Fallback: _______________________

----------------------------------------------------------------

SHOULD CHANGE (Important but not deal breakers):

1. Issue: _______________________
Proposed change: _______________________

2. Issue: _______________________
Proposed change: _______________________

----------------------------------------------------------------

NICE TO CHANGE (Improvements if possible):

1. _______________________
2. _______________________

----------------------------------------------------------------

NEGOTIATION STRATEGY:

Lead negotiator: _______________________
Approach: _______________________
Authority level: _______________________

================================================================

Approval Requirements​

Contract Approval Matrix:​

Contract ValueRisk LevelApprover
AnyUnacceptableDo not bid
under $500KLow/MediumPM + Estimating Mgr
under $500KHighVP Operations
$500K-$2MAnyVP Operations
$2M-$5MAnyCFO + VP Operations
over $5MAnyCEO/Owner

Pre-Signature Checklist:​

================================================================
CONTRACT SIGNING CHECKLIST
================================================================

☐ Contract reviewed by appropriate level
☐ All negotiated changes incorporated
☐ Insurance requirements met
☐ Bonding confirmed (if required)
☐ Risk assessment documented
☐ Appropriate signature authority
☐ Contract value within authority limits

Signed by: _______________________
Date: _______________________

================================================================

Subcontract Flow-Down​

Subcontract Risk Review:​

When we are the GC, ensure subcontracts:

  • Flow down relevant prime contract terms
  • Include appropriate indemnification
  • Match insurance requirements
  • Include dispute provisions
  • Don't create gaps in coverage

  • Go/No-Go Decision Process
  • Insurance Requirements
  • Lien Rights
  • Change Order Management