Labor Productivity Analysis

Document Type: Guide
Version: 1.0
Last Updated: February 2026
Distribute To: CFO, Controller, Operations Manager, Project Managers


Purpose​

Establish procedures for measuring, analyzing, and improving labor productivity to enhance profitability, improve estimates, and optimize workforce management.


Why Labor Productivity Matters​

Construction Labor Reality:​

  • Labor typically 30-50% of project cost
  • Small productivity changes = big profit impact
  • Productivity varies widely (up to 50% between crews)
  • Measurement enables improvement

Impact Example:​

10% productivity improvement on $1M labor budget:
= $100,000 savings
= Direct contribution to profit
= Often makes difference between profit and loss

Productivity Metrics​

Basic Productivity Formula:​

Productivity = Output Γ· Input

Construction examples:
- Linear feet of pipe per hour
- Square feet of drywall per hour
- Cubic yards of concrete per hour
- Units installed per hour

Key Metrics:​

MetricFormulaUse
Labor FactorActual Hours Γ· Budget HoursOverall efficiency
Unit RateHours Γ· Units InstalledSpecific activity
Cost per UnitLabor $ Γ· Units InstalledCost tracking
Revenue per HourRevenue Γ· Labor HoursCompany-wide

Measuring Productivity​

Daily Production Report:​

================================================================
DAILY PRODUCTION REPORT
================================================================

Project: _______________________ Date: _______________
Foreman/Super: _______________________

================================================================

LABOR:

| Employee | Classification | Hours | Cost Code |
|----------|----------------|-------|-----------|
| | | | |
| | | | |
| | | | |

Total crew size: _____
Total hours: _____

----------------------------------------------------------------

PRODUCTION:

| Activity | Cost Code | Units | Unit Type | Hours |
|----------|-----------|-------|-----------|-------|
| | | | | |
| | | | | |

Productivity: _____ units/hour

Budget productivity: _____ units/hour

Performance: _____% of budget

----------------------------------------------------------------

CONDITIONS:

Weather: ☐ Normal ☐ Hot ☐ Cold ☐ Rain ☐ Wind
Site access: ☐ Good ☐ Limited ☐ Poor
Material availability: ☐ Good ☐ Some delays ☐ Waiting
Equipment availability: ☐ Good ☐ Issues: _________________
Coordination with others: ☐ Good ☐ Conflicts

----------------------------------------------------------------

ISSUES/DELAYS:

| Issue | Hours Lost | Impact |
|-------|------------|--------|
| | | |

----------------------------------------------------------------

TOMORROW'S PLAN:

Activity: _______________________
Target production: _______________________
Resources needed: _______________________

================================================================

Weekly Productivity Summary:​

================================================================
WEEKLY PRODUCTIVITY SUMMARY
================================================================

Project: _______________________ Week Ending: _______________

================================================================

LABOR SUMMARY:

| Cost Code | Description | Budget | Actual | Variance | % |
|-----------|-------------|--------|--------|----------|---|
| | | | | | |
| | | | | | |
| TOTAL | | | | | |

Overall labor factor: _____
over 1.0 = Using more hours than budget (inefficient)
under 1.0 = Using fewer hours than budget (efficient)

----------------------------------------------------------------

PRODUCTION BY ACTIVITY:

| Activity | Units | Hours | Unit/Hr | Budget | % Budget |
|----------|-------|-------|---------|--------|----------|
| | | | | | |

----------------------------------------------------------------

PRODUCTIVITY TREND:

| Week | Labor Factor | Best Day | Worst Day |
|------|--------------|----------|-----------|
| -4 | | | |
| -3 | | | |
| -2 | | | |
| -1 | | | |
| This | | | |

Trend: ☐ Improving ☐ Stable ☐ Declining

================================================================

Productivity Analysis​

Labor Factor Analysis:​

================================================================
LABOR FACTOR ANALYSIS
================================================================

Project: _______________________ Through: _______________

================================================================

BY COST CODE:

| Cost Code | Description | Budget Hrs | Actual Hrs | Factor |
|-----------|-------------|------------|------------|--------|
| | | | | |
| | | | | |
| PROJECT | | | | |

----------------------------------------------------------------

BEST PERFORMING (Factor < 0.95):

| Cost Code | Factor | Reason for Good Performance |
|-----------|--------|----------------------------|
| | | |

----------------------------------------------------------------

WORST PERFORMING (Factor > 1.05):

| Cost Code | Factor | Reason | Corrective Action |
|-----------|--------|--------|-------------------|
| | | | |

----------------------------------------------------------------

ROOT CAUSE ANALYSIS:

High labor factors typically caused by:
☐ Estimating error (budget too low)
☐ Scope creep (more work than estimated)
☐ Rework/quality issues
☐ Material/equipment delays
☐ Crew inexperience
☐ Supervision gaps
☐ Site conditions
☐ Weather impacts
☐ Coordination issues
☐ Other: _______________________________

Action plan:
___________________________________________________________

================================================================

Productivity by Crew:​

================================================================
CREW PRODUCTIVITY COMPARISON
================================================================

Project: _______________________ Activity: _______________

================================================================

| Crew/Foreman | Hours | Units | Productivity | % of Best |
|--------------|-------|-------|--------------|-----------|
| Crew A | | | | |
| Crew B | | | | |
| Crew C | | | | |
| AVERAGE | | | | |

Best crew: _______________________
Gap from best to worst: _____%

----------------------------------------------------------------

ANALYSIS:

What makes the best crew more productive?
☐ Experience level
☐ Crew composition
☐ Leadership/supervision
☐ Planning/organization
☐ Tool/equipment management
☐ Work habits
☐ Other: _______________________________

Improvement opportunity if all crews matched best:
Hours saved: _____
Dollar savings: $_________________

================================================================

Productivity Factors​

Factors Affecting Productivity:​

FactorImpact RangeControllable?
Crew experienceΒ±30%Partially
Supervision qualityΒ±25%Yes
Planning/schedulingΒ±20%Yes
Material availabilityΒ±20%Yes
Tool/equipmentΒ±15%Yes
WeatherΒ±15%No
Site conditionsΒ±15%Partially
Overtime fatigue-10-25%Yes
Learning curve-20% initialExpected
Rework-5-15%Yes

Adjustment Factors:​

================================================================
PRODUCTIVITY ADJUSTMENT FACTORS
================================================================

Standard productivity rate: _____ units/hour

ADJUSTMENT FOR CONDITIONS:

| Condition | Factor | Adjusted Rate |
|-----------|--------|---------------|
| Overtime (over 40 hrs/wk) | 0.90 | |
| Overtime (over 50 hrs/wk) | 0.80 | |
| Hot weather (over 95Β°F) | 0.85 | |
| Cold weather (under 32Β°F) | 0.85 | |
| Confined space | 0.75 | |
| Heights (over 30 ft) | 0.85 | |
| Occupied building | 0.85 | |
| Remote location | 0.90 | |
| Night shift | 0.90 | |
| New crew/learning | 0.75 | |

Applied adjustment: _____
Adjusted productivity: _____ units/hour

================================================================

Improving Productivity​

Productivity Improvement Plan:​

================================================================
PRODUCTIVITY IMPROVEMENT PLAN
================================================================

Project: _______________________ Prepared: _______________

Current overall labor factor: _____
Target labor factor: _____
Improvement needed: _____%

----------------------------------------------------------------

IMPROVEMENT INITIATIVES:

1. PLANNING & SCHEDULING:
☐ Detailed daily work plans
☐ Look-ahead scheduling
☐ Pre-task briefings
Expected impact: _____% improvement

2. MATERIAL MANAGEMENT:
☐ Material staged before work
☐ Just-in-time delivery
☐ Kitting/pre-assembly
Expected impact: _____% improvement

3. TOOL & EQUIPMENT:
☐ Right tools available
☐ Equipment maintained
☐ Specialized tools where needed
Expected impact: _____% improvement

4. CREW OPTIMIZATION:
☐ Right crew size
☐ Skill matching to work
☐ Consistent crew assignments
Expected impact: _____% improvement

5. SUPERVISION:
☐ Adequate span of control
☐ Clear expectations
☐ Regular feedback
Expected impact: _____% improvement

----------------------------------------------------------------

IMPLEMENTATION:

| Initiative | Owner | Start Date | Target Improvement |
|------------|-------|------------|-------------------|
| | | | |

Measurement: Weekly labor factor tracking
Review: Weekly PM review

================================================================

Quick Productivity Wins:​

ActionTypical ImpactImplementation
Start on time3-5%Enforce start times
Reduce travel time2-4%Stage materials nearby
Pre-task planning5-10%Morning briefings
Tool organization2-3%Job boxes, shadow boards
Material staging5-8%Night/early delivery
Reduce rework5-10%Quality checks
Minimize overtime5-15%Better planning

Estimating Feedback​

Productivity Database Update:​

================================================================
PRODUCTIVITY DATA UPDATE
================================================================

Activity: _______________________
Project: _______________________

================================================================

HISTORICAL DATA:

| Project | Year | Units | Hours | Productivity | Conditions |
|---------|------|-------|-------|--------------|------------|
| | | | | | |
| | | | | | |
| | | | | | |

Historical average: _____ units/hour
Standard deviation: _____

----------------------------------------------------------------

THIS PROJECT:

Units: _____
Hours: _____
Productivity: _____ units/hour

Conditions: _______________________

Variance from average: _____%

----------------------------------------------------------------

DATABASE UPDATE:

☐ Update estimating database
☐ Update crew planning
☐ Document lessons learned

New recommended rate: _____ units/hour

Approved by: _______________________

================================================================

Reporting​

Monthly Productivity Report:​

================================================================
MONTHLY PRODUCTIVITY REPORT
================================================================

Month: _______________

================================================================

COMPANY SUMMARY:

Revenue: $_________________
Total labor hours: _____
Revenue per labor hour: $_____
Target: $_____
Variance: $_____

----------------------------------------------------------------

BY PROJECT:

| Project | Labor Factor | This Month | YTD | Trend |
|---------|--------------|------------|-----|-------|
| | | | | ↑↓→ |
| | | | | ↑↓→ |
| AVERAGE | | | | |

----------------------------------------------------------------

TOP PERFORMERS:

| Project | Labor Factor | Key Success Factors |
|---------|--------------|---------------------|
| | | |

----------------------------------------------------------------

NEEDS IMPROVEMENT:

| Project | Labor Factor | Issues | Action Plan |
|---------|--------------|--------|-------------|
| | | | |

----------------------------------------------------------------

PRODUCTIVITY INITIATIVES:

| Initiative | Status | Measured Impact |
|------------|--------|-----------------|
| | | |

================================================================

Software Integration​

BLDR Time Integration:​

  • Real-time labor hour capture
  • GPS verification of on-site time
  • Cost code allocation
  • Automatic productivity calculation
  • Dashboard visibility

Benefits:​

  • Accurate data
  • Less administrative burden
  • Real-time visibility
  • Trend analysis
  • Crew comparisons

  • Job Costing Procedures
  • Time Tracking Procedures
  • Estimating Standards
  • Cost Control Procedures