Subcontract Execution Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Legal, Operations


Purpose

Establish the process for executing subcontract agreements to ensure proper scope definition, risk management, and contract compliance.


When to Execute Subcontract

Before Work Begins

  • ALWAYS have executed subcontract before work starts
  • No verbal agreements for scope of work
  • No "handshake deals"

Timeline

  • Award: Verbally communicate selection
  • Draft: Send within 3-5 days
  • Execute: Before mobilization
  • Minimum: 7 days before work starts

Subcontract Components

Essential Elements

SectionContent
PartiesFull legal names, addresses
ProjectName, location, description
ScopeDetailed work description
PriceLump sum or unit prices
ScheduleStart, duration, milestones
TermsPayment, changes, disputes
ExhibitsDrawings, specs, insurance

Scope of Work Development

Clear Scope Definition

Include:

  • Work to be performed
  • Materials/equipment to provide
  • Labor classifications required
  • Quality standards
  • Code requirements
  • Coordination requirements

Specifically Address:

  • Inclusions (what's in)
  • Exclusions (what's out)
  • Allowances (if any)
  • Alternates (if applicable)

Scope Clarity Checklist:

  • Referenced drawings listed
  • Specification sections listed
  • Physical boundaries defined
  • Interfaces with other trades clear
  • Exclusions explicitly stated
  • General conditions items addressed

Subcontract Review Checklist

Before Sending for Signature:

Scope:

  • Scope matches bid/proposal
  • Inclusions/exclusions clear
  • Drawings/specs referenced

Commercial:

  • Price correct
  • Payment terms stated
  • Retainage terms included
  • Change order process defined

Schedule:

  • Start date stated
  • Duration or completion date
  • Milestone dates (if applicable)
  • Liquidated damages (if applicable)

Insurance:

  • Minimum limits specified
  • Additional insured required
  • Certificate due date

Legal:

  • Indemnification clause
  • Dispute resolution
  • Termination provisions
  • Compliance requirements

Attachments:

  • Scope exhibit
  • Drawings list
  • Specification sections
  • Insurance requirements
  • Safety requirements

Key Subcontract Clauses

Payment Terms

  • Monthly billing cycle
  • Pay application requirements
  • Lien waiver requirements
  • Retainage terms
  • Final payment conditions

Change Orders

  • Written authorization required
  • Pricing methodology
  • Markup limitations
  • Time for response

Schedule

  • Coordination required
  • Notice of delays
  • Acceleration rights
  • Float ownership

Quality

  • Work standards
  • Inspection requirements
  • Correction of defects
  • Warranty obligations

Safety

  • Compliance with laws
  • Safety program requirements
  • Drug testing
  • Incident reporting

Insurance

  • Types and limits
  • Additional insured
  • Waiver of subrogation
  • Certificate requirements

Subcontract Execution Process

Step 1: Prepare Draft

  1. Use company template
  2. Insert project-specific info
  3. Develop scope exhibit
  4. List attachments
  5. Internal review

Step 2: Send to Subcontractor

  1. Transmit with cover letter
  2. Set response deadline (typically 5 days)
  3. Note insurance due date
  4. Request acknowledgment

Step 3: Subcontractor Review

  • Allow time for review
  • Be open to reasonable changes
  • Negotiate if needed
  • Document any changes

Step 4: Execute

  1. Sub signs and returns
  2. GC reviews signed copy
  3. GC countersigns
  4. Distribute fully executed copy

Step 5: Post-Execution

  • Scan and file
  • Enter in commitment log
  • Collect insurance certificate
  • Schedule kickoff meeting
  • Issue Notice to Proceed

Insurance Certificate Requirements

Before Work Begins:

  • Certificate received
  • Limits meet requirements
  • Project listed
  • Additional insured endorsement
  • Certificate holder correct
  • Expiration date noted

Monitor:

  • Track expiration dates
  • Request renewals 30 days ahead
  • No work without current insurance

Subcontract Agreement Quick Form

================================================================
SUBCONTRACT AGREEMENT
================================================================

This Agreement made [Date], between:

CONTRACTOR: _______________________________________________
Address: _________________________________________________

SUBCONTRACTOR: ___________________________________________
Address: _________________________________________________

PROJECT: _________________________________________________
Location: ________________________________________________

================================================================

1. SCOPE OF WORK
Subcontractor shall furnish all labor, materials, equipment,
and supervision necessary to complete the work described in
Exhibit A (Scope of Work) and the following specification
sections: [List sections]

2. CONTRACT SUM
☐ Lump Sum: $______________
☐ Unit Prices: See Exhibit B
☐ Time & Material: Not to exceed $______________

3. SCHEDULE
Start Date: _______________
Completion Date: _______________
Duration: _______________

4. PAYMENT TERMS
Progress payments monthly, Net _____ days
Retainage: _____% until _____________

5. INSURANCE REQUIREMENTS
See Exhibit C - Insurance Requirements
Certificate due within _____ days

6. INCORPORATED DOCUMENTS
☐ Prime Contract (relevant portions)
☐ Project specifications
☐ Project drawings
☐ Safety requirements
☐ Insurance requirements

================================================================

CONTRACTOR SUBCONTRACTOR

By: ________________________ By: ________________________

Name: ______________________ Name: ______________________

Title: _____________________ Title: _____________________

Date: ______________________ Date: ______________________

================================================================

  • Subcontract Template (full form)
  • Scope of Work Exhibit Template
  • Insurance Requirements Exhibit
  • Prequalification Procedure
  • Change Order Procedure

Software Integration

BLDR Pro:

  • Commitment tracking
  • Document storage
  • Insurance monitoring
  • Change order tracking

Template provided by support.construction. Customize with your company information.