Crew Management Procedures

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Foremen, Superintendents, Project Managers


Purposeโ€‹

Establish procedures for effective crew management including scheduling, productivity tracking, and resource optimization.


Crew Management Overviewโ€‹

Effective crew management directly impacts:

  • Project profitability (labor is 30-50% of cost)
  • Schedule performance
  • Quality of work
  • Safety outcomes
  • Worker satisfaction/retention

Crew Schedulingโ€‹

Weekly Planning:โ€‹

By Thursday/Friday for Next Week:

  1. Review project schedule
  2. Identify labor needs by project
  3. Check crew availability
  4. Assign crews to projects
  5. Communicate assignments

Crew Assignment Factors:โ€‹

FactorConsideration
Skills neededMatch crew capabilities to work
Project phaseRight crew size for phase
Productivity historyAssign best crews to critical work
Travel distanceMinimize windshield time
ContinuityKeep crews on same project when possible

Crew Schedule Template:โ€‹

================================================================
WEEKLY CREW SCHEDULE
================================================================

Week Of: ___________________________________________________

================================================================

| Crew | Mon | Tue | Wed | Thu | Fri | Sat |
|------|-----|-----|-----|-----|-----|-----|
| A - [Foreman] | | | | | | |
| B - [Foreman] | | | | | | |
| C - [Foreman] | | | | | | |

================================================================

NOTES:
___________________________________________________________

================================================================

Daily Crew Managementโ€‹

Start of Day:โ€‹

Foreman Responsibilities:

  • Review day's work plan
  • Conduct pre-task safety briefing
  • Assign specific tasks to workers
  • Ensure materials/equipment ready
  • Confirm crew understands expectations

During the Day:โ€‹

  • Monitor progress vs. plan
  • Address obstacles
  • Adjust assignments as needed
  • Maintain quality standards
  • Enforce safety requirements

End of Day:โ€‹

  • Verify work completed
  • Record time accurately
  • Document progress
  • Plan for tomorrow
  • Report issues to PM/Super

Time Trackingโ€‹

Accurate Time Tracking Critical For:โ€‹

  • Payroll accuracy
  • Job costing
  • Productivity analysis
  • Certified payroll compliance
  • Billing justification

Time Recording Requirements:โ€‹

ElementRequired
ProjectYes
Cost codeYes
ClassificationYes (prevailing wage)
Start/end timeYes
BreaksYes (California)
Description of workRecommended

GPS Time Tracking Benefits:โ€‹

  • Eliminates buddy punching
  • Proves job site presence
  • Accurate to-the-minute records
  • Automatic travel time tracking
  • Audit-ready documentation

Software Integration:โ€‹

BLDR Time:

  • Mobile clock-in/out with GPS
  • Project/cost code selection
  • Automatic prevailing wage compliance
  • Crew time approval workflow
  • Integration with payroll

Productivity Trackingโ€‹

Measuring Productivity:โ€‹

Productivity = Units Completed รท Labor Hours

Example:
- 500 SF drywall installed
- 16 labor hours
- Productivity: 31.25 SF/hour

Productivity Benchmarks:โ€‹

Track productivity against:

  • Estimate assumptions
  • Historical performance
  • Industry standards
  • Same crew on same project (trend)

Productivity Report:โ€‹

================================================================
CREW PRODUCTIVITY REPORT
================================================================

Project: ___________________ Period: ______________________

Crew: _____________________ Foreman: _____________________

================================================================

| Work Item | Unit | Budget | Actual | Variance |
|-----------|------|--------|--------|----------|
| | | | | |
| | | | | |
| | | | | |

================================================================

Overall Productivity: ____% of budget

Issues Affecting Productivity:
___________________________________________________________

Corrective Actions:
___________________________________________________________

================================================================

Crew Performance Managementโ€‹

Performance Factors:โ€‹

FactorHow to Measure
ProductivityUnits per hour vs. budget
QualityRework, punch list items
SafetyIncidents, observations
AttendanceDays worked vs. scheduled
TeamworkPeer/supervisor feedback

High-Performing Crews:โ€‹

  • Recognize and reward
  • Assign to critical work
  • Use as training resource
  • Consider for leadership

Underperforming Crews:โ€‹

  • Identify root causes
  • Provide training/support
  • Address specific issues
  • Make changes if needed

Labor Optimizationโ€‹

Right-Sizing Crews:โ€‹

Too Many Workers:

  • Stacking and interference
  • Reduced productivity
  • Wasted labor cost

Too Few Workers:

  • Missed deadlines
  • Overtime costs
  • Worker burnout

Optimal Crew Size:โ€‹

  • Based on scope of work
  • Consider workspace size
  • Account for support tasks
  • Include apprentice ratios

Overtime Management:โ€‹

OvertimeImpact
0-10 hrs/weekMinimal productivity loss
10-20 hrs/week5-10% productivity loss
20+ hrs/week15-25% productivity loss

Use overtime strategically, not routinely


Crew Communicationโ€‹

Daily:โ€‹

  • Pre-task briefings
  • Progress updates
  • Issue escalation
  • End-of-day debrief

Weekly:โ€‹

  • Schedule communication
  • Performance feedback
  • Safety topics
  • Company updates

Tools:โ€‹

  • In-person meetings
  • Text/messaging apps
  • Radio communication
  • Project management software

Multi-Project Crew Managementโ€‹

When Crews Work Multiple Projects:โ€‹

Challenges:

  • Travel time
  • Context switching
  • Split accountability
  • Time tracking complexity

Best Practices:

  • Minimize project switches per day
  • Group nearby projects
  • Clear time allocation rules
  • GPS tracking for accuracy

  • Timesheet Procedure
  • Certified Payroll
  • Productivity Tracking
  • Pre-Task Planning

Software Integrationโ€‹

BLDR Time:

  • Crew time tracking
  • GPS verification
  • Multi-project allocation
  • Productivity reporting
  • Payroll integration

BLDR Pro:

  • Daily reports
  • Work completion tracking
  • Photo documentation
  • Progress tracking

Template provided by support.construction. Effective crew management drives profitability.