Final Documentation Package Procedure
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Project Engineers, Admin
Purpose
Establish requirements for assembling and delivering the final documentation package required for project closeout.
Documentation Package Components
Required Closeout Documents
| Document | Source | Copies |
|---|---|---|
| As-Built Drawings | Contractor | Per contract |
| O&M Manuals | Subs/Manufacturers | Per spec |
| Warranties | Subs/Manufacturers | Originals |
| Test Reports | Testing agencies | All |
| Certifications | Various | All |
| Spare Parts | Per spec | As specified |
| Training | Contractor/Subs | Documentation |
As-Built Drawings
Requirements:
- Show actual installed conditions
- Mark all deviations from design
- Include field changes
- Note concealed conditions
Process:
- Maintain red-lines throughout project
- Mark changes as they occur
- Include RFI/ASI changes
- Compile at end of project
- Create final as-builts
Content:
- Underground utilities (depths, locations)
- MEP routing changes
- Structural changes
- Finish changes
- Equipment locations
Format:
- Per contract (CAD, PDF, or marked prints)
- Clear and legible
- Dated and signed
O&M Manuals
Required Content:
- Equipment data sheets
- Parts lists
- Operating instructions
- Maintenance schedules
- Troubleshooting guides
- Contact information
Organization:
Volume 1: General
- Index
- Project data
- Equipment summary
Volume 2: Mechanical
- HVAC equipment
- Plumbing equipment
- Fire protection
Volume 3: Electrical
- Switchgear
- Lighting
- Low voltage systems
Volume 4: Specialty
- Elevators
- Fire alarm
- Security
Collection Process:
- Identify required manuals (specifications)
- Request from subcontractors early
- Review for completeness
- Compile and organize
- Deliver per contract
Warranties
Standard Warranty Requirements:
| Item | Typical Duration |
|---|---|
| General construction | 1 year |
| Roofing | 10-20 years |
| HVAC equipment | 1-5 years |
| Plumbing fixtures | 1-5 years |
| Electrical equipment | 1-5 years |
| Windows/glazing | 5-10 years |
Warranty Documentation:
- Manufacturer warranties (original)
- Installation warranty letters
- Start date (usually substantial completion)
- Contact information
- Claim procedures
Warranty Letter Format:
[Subcontractor Letterhead]
ROOFING WARRANTY
Project: [Name]
Location: [Address]
Owner: [Name]
We hereby warrant that the roofing system installed at the
above project will be free from defects in materials and
workmanship for a period of [X] years from [Date].
This warranty covers:
- [List covered items]
This warranty does not cover:
- [List exclusions]
To file a warranty claim, contact:
[Contact information]
_____________________________
[Authorized Signature]
[Date]
Test Reports and Certifications
Common Required Tests:
| System | Test | Documentation |
|---|---|---|
| Concrete | Compressive strength | Cylinder break reports |
| Steel | Welds, bolts | Inspection reports |
| Plumbing | Pressure test | Test certificate |
| HVAC | Balancing | TAB report |
| Electrical | Megger, ground | Test reports |
| Fire alarm | Acceptance test | Certification |
| Fire sprinkler | Hydro test | Certification |
| Elevator | Acceptance | Inspection certificate |
Collecting Test Reports:
- Track required tests (specification)
- Schedule testing
- Witness tests (if required)
- Obtain reports
- Review for compliance
- Address failures
- Compile for closeout
Spare Parts and Attic Stock
Common Requirements:
| Item | Typical Quantity |
|---|---|
| Ceiling tiles | 2% of installed |
| Floor tile | 2% of installed |
| Paint | 1 gallon each color |
| Filters | 1 set |
| Lamps/bulbs | 2% of installed |
| Ceiling grid | 2% of installed |
| Hardware | 2% of each type |
Delivery:
- Labeled with location/use
- Stored in designated area
- Inventory list provided
- Receipt obtained from owner
Training
Required Training:
| System | Trainer | Duration | Attendees |
|---|---|---|---|
| HVAC | Mechanical sub | 2-4 hours | Maintenance |
| Fire alarm | Fire alarm sub | 2 hours | Maintenance/security |
| BMS | Controls sub | 4-8 hours | Maintenance |
| Elevator | Elevator company | 1-2 hours | Maintenance |
| Security | Security sub | 2-4 hours | Security staff |
Documentation:
- Training sign-in sheets
- Training materials provided
- Video recording (if permitted)
- Contact for follow-up
Documentation Submission Checklist
================================================================
CLOSEOUT DOCUMENTATION CHECKLIST
================================================================
Project: _________________________ Date: _______________
DOCUMENTS TO SUBMIT:
As-Built Drawings
☐ Architectural
☐ Structural
☐ Mechanical
☐ Electrical
☐ Plumbing
☐ Civil/Site
O&M Manuals
☐ Mechanical systems
☐ Electrical systems
☐ Plumbing
☐ Fire protection
☐ Specialty systems
☐ [Other]
Warranties
☐ General construction warranty letter
☐ Roofing warranty
☐ Equipment warranties
☐ Special warranties per spec
Test Reports
☐ Concrete test reports
☐ Steel inspection reports
☐ MEP test reports
☐ TAB report
☐ Commissioning report (if required)
☐ Special inspection reports
Certifications
☐ Elevator certification
☐ Fire alarm certificate
☐ Fire sprinkler certificate
☐ Electrical inspection
☐ [Other]
Keys and Access
☐ Building keys
☐ Mechanical keys
☐ Access cards/codes
☐ Key schedule
Spare Parts
☐ Ceiling tiles
☐ Floor materials
☐ Paint
☐ Filters
☐ [Per specification]
Training
☐ Training completed
☐ Sign-in sheets
☐ Materials provided
SUBMITTED BY: ________________________ DATE: ____________
RECEIVED BY: _________________________ DATE: ____________
================================================================
Submission Process
Timeline:
- Begin collection at 80% complete
- Submit draft 2 weeks before S.C.
- Address comments
- Final submission at final completion
- Obtain receipt
Format:
- Per contract requirements
- Typically 3 sets + electronic
- Organized per spec/owner requirements
- Clear labeling
Related Documents
- Punch List Procedure
- Substantial Completion
- Final Pay Application
- Warranty Tracking
Software Integration
BLDR Pro:
- Document tracking
- Submission checklists
- Electronic storage
- Distribution tracking
Template provided by support.construction. Customize with your company information.