Skip to main content
Skip to main content

Financial Closeout Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Accounting


Purpose

Establish procedures for completing project financial closeout to ensure all costs are captured, revenues collected, and profitability calculated.


Financial Closeout Timeline

ActivityTiming
Final change ordersBefore final billing
Sub final paymentsWithin 30 days of completion
Final pay applicationPer contract
Retention collectionPer contract
Cost reconciliationWithin 60 days
Profit/loss analysisWithin 90 days
Job closeoutWithin 120 days

Financial Closeout Steps

Step 1: Process Final Change Orders

Before Final Billing:

  • All change orders submitted
  • All change orders approved
  • All change orders billed
  • No pending changes

Step 2: Finalize Subcontractor Payments

For Each Subcontractor:

  • Final pay application received
  • Punch list complete
  • Backcharges processed
  • Final lien waiver collected
  • Final payment processed

Step 3: Finalize Vendor Payments

For Each Vendor:

  • All invoices received
  • All invoices paid
  • Credits applied
  • Accounts closed

Step 4: Submit Final Pay Application

Final Billing Includes:

  • All remaining contract work
  • All approved change orders
  • Retention release request
  • Final lien waivers

Step 5: Collect Final Payment and Retention

Track:

  • Final payment received
  • Retention received
  • All funds collected

Step 6: Reconcile Job Costs

Compare:

  • Budget vs. actual (by cost code)
  • Identify variances
  • Explain significant differences
  • Document lessons learned

Step 7: Calculate Final Profit/Loss

Financial Summary:

  • Total contract value
  • Total costs
  • Gross profit
  • Gross margin %

Step 8: Close Project in System

Final Actions:

  • Close all purchase orders
  • Close job in accounting
  • Archive project files
  • Complete closeout report

Job Cost Reconciliation

Cost Comparison:

Cost CodeBudgetActualVariance%
Labor
Material
Equipment
Subcontract
Other
TOTAL

Variance Analysis:

  • Identify major variances (> 5%)
  • Determine causes
  • Document for future estimates

Financial Closeout Checklist

================================================================
PROJECT FINANCIAL CLOSEOUT CHECKLIST
================================================================

Project: _____________________ Project #: ____________________

PM: _________________________ Close Date: ___________________

================================================================

CHANGE ORDERS:
☐ All COs submitted
☐ All COs approved
☐ All COs billed
☐ Final CO log complete

SUBCONTRACTORS:
☐ All final pay apps processed
☐ All backcharges processed
☐ All final lien waivers collected
☐ All final payments made

VENDORS/SUPPLIERS:
☐ All invoices received
☐ All invoices paid
☐ All credits applied

BILLING:
☐ Final pay application submitted
☐ Final payment received
☐ Retention received
☐ All funds collected

JOB COSTS:
☐ All costs posted
☐ All time charged
☐ Cost reconciliation complete
☐ Variances analyzed

FINANCIAL:
☐ Profit/loss calculated
☐ Margin % calculated
☐ Closeout report complete

ADMINISTRATIVE:
☐ Job closed in accounting system
☐ POs closed
☐ Files archived
☐ Lessons learned documented

================================================================

FINAL PROJECT FINANCIAL SUMMARY:

Original Contract: $____________________
Change Orders: $____________________
Final Contract Value: $____________________

Total Costs: $____________________

Gross Profit: $____________________
Gross Margin: ________%

================================================================

PM Signature: _______________________ Date: _________________

Accounting: _________________________ Date: _________________

================================================================

Profit/Loss Analysis

Final Project P&L:

CONTRACT REVENUE:
Original Contract $__________
Change Orders $__________
Total Revenue $__________

DIRECT COSTS:
Labor $__________
Material $__________
Equipment $__________
Subcontracts $__________
Other Direct $__________
Total Direct Costs $__________

GROSS PROFIT $__________

GROSS MARGIN ________%

INDIRECT COSTS:
General Conditions $__________
Warranty Reserve $__________
Total Indirect $__________

NET PROFIT $__________
NET MARGIN ________%

  • Final Pay Application
  • Retention Release Request
  • Sub Final Payment Process
  • Lessons Learned Report

Template provided by support.construction. Customize with your company information.