Skip to main content
Skip to main content

๐Ÿ’ต Progress Billing Calculator

Calculate schedule of values, percent complete, and pay application amounts.


How Progress Billing Worksโ€‹

Current Payment Due = (% Complete ร— Contract Value) - Previous Payments - Retention

The Billing Cycleโ€‹

  1. Schedule of Values (SOV) โ€” Break contract into line items
  2. Track Progress โ€” Determine % complete each period
  3. Apply Retention โ€” Typically 5-10% withheld
  4. Submit Pay App โ€” Request payment for completed work
  5. Receive Payment โ€” Usually 30 days after approval

Schedule of Values Setupโ€‹

Front-Loading Considerationsโ€‹

Ethical Note

Front-loading (inflating early work items) is common but can create problems. Balance cash flow needs with accuracy.

Sample SOV Breakdownโ€‹

ItemDescriptionValue% of Contract
1General Conditions$50,0005%
2Site Work$100,00010%
3Foundation$150,00015%
4Structural$200,00020%
5MEP Rough-in$150,00015%
6Exterior$100,00010%
7Interior Finishes$150,00015%
8MEP Finish$75,0007.5%
9Closeout$25,0002.5%
TOTAL$1,000,000100%

Percent Complete Methodsโ€‹

Method 1: Units Completedโ€‹

Best for repetitive work (footings, doors, fixtures).

% Complete = Units Installed รท Total Units

Example: 40 of 100 doors installed = 40% complete

Method 2: Cost-to-Costโ€‹

Best for complex work, most accurate.

% Complete = Costs Incurred to Date รท Estimated Total Costs

Example: $75,000 spent on $150,000 budgeted item = 50% complete

Method 3: Physical Observationโ€‹

Subjective estimate based on visual inspection.

  • Good for: Materials, general conditions
  • Risk: Disputes over interpretation

Pay Application Calculatorโ€‹

Single Line Item Exampleโ€‹

FieldValue
A. Contract Value$150,000
B. % Complete This Period35%
C. Value of Work (A ร— B)$52,500
D. Previous Billings$30,000
E. Current Billing (C - D)$22,500
F. Retention Rate10%
G. Retention Amount (E ร— F)$2,250
H. Net Due This Period (E - G)$20,250

Full Pay Application Exampleโ€‹

Project: $1,000,000 Contract, 10% Retention, Period 3โ€‹

LineDescriptionSOV ValuePrevious %Current %Previous BillingCurrent BillingRetentionNet Due
1General Conditions$50,00030%45%$15,000$7,500$750$6,750
2Site Work$100,00090%100%$90,000$10,000$1,000$9,000
3Foundation$150,000100%100%$150,000$0$0$0
4Structural$200,00050%75%$100,000$50,000$5,000$45,000
5MEP Rough-in$150,00020%40%$30,000$30,000$3,000$27,000
6Exterior$100,0000%15%$0$15,000$1,500$13,500
7Interior Finishes$150,0000%0%$0$0$0$0
8MEP Finish$75,0000%0%$0$0$0$0
9Closeout$25,0000%0%$0$0$0$0
TOTALS$1,000,000$385,000$112,500$11,250$101,250

Pay Application Summaryโ€‹

DescriptionAmount
Original Contract$1,000,000
Approved Change Orders$0
Adjusted Contract$1,000,000
Total Completed to Date$497,500
Total Retention (10%)$49,750
Total Earned Less Retention$447,750
Less Previous Payments$346,500
Current Payment Due$101,250

Retention Calculationsโ€‹

Standard Retention Ratesโ€‹

Project TypeTypical Rate
Commercial10%
Public works5% (often capped)
Residential10%
Federal0-10% (varies)

Retention Reductionโ€‹

Many contracts allow retention reduction at substantial completion:

MilestoneRetention Rate
0-50% complete10%
50-95% complete10% (or reduce to 5%)
Substantial completionReduce to 5% or release
Final completionRelease remaining

Retention Release Calculationโ€‹

At substantial completion (reducing from 10% to 5%):

Retention to Release = Total Retention Held - (Contract ร— 5%)

Example: $1M contract at 95% complete

  • Retention held: $95,000 (10% of $950,000)
  • New retention needed: $50,000 (5% of $1,000,000)
  • Release amount: $45,000

Stored Materials Billingโ€‹

What Can Be Billedโ€‹

  • Materials purchased for the project
  • Stored on-site or in approved off-site location
  • Proper documentation (invoices, photos)

Stored Materials Formatโ€‹

MaterialInvoice CostMarkup (if allowed)Billable Amount
Steel$25,0000%$25,000
Fixtures$15,0000%$15,000
Equipment$30,0000%$30,000
Total Stored Materials$70,000

Documentation Requiredโ€‹

  • Supplier invoices
  • Proof of payment (often required)
  • Photos of stored materials
  • Evidence of proper storage/protection
  • Insurance certificate for off-site storage

Change Order Billingโ€‹

Adding Change Orders to Pay Appโ€‹

DescriptionOriginal ContractApproved COsAdjusted Contract
Base contract$1,000,000
CO #1 - Added scope+$25,000
CO #2 - Owner change+$15,000
CO #3 - Credit-$5,000
ADJUSTED TOTAL$1,035,000

Change Order Progressโ€‹

Bill change orders separately or add to SOV:

CO #DescriptionValue% CompleteBilled This Period
1Added electrical$25,00080%$5,000
2Window upgrade$15,000100%$15,000
3Credit - deleted door-$5,000100%-$5,000

Cash Flow Projectionโ€‹

Project Cash Flow Timelineโ€‹

Using the $1M example project over 12 months:

Month% CompleteGross BillingRetentionNet Received*Cumulative
18%$80,000$8,000$72,000$72,000
220%$120,000$12,000$108,000$180,000
335%$150,000$15,000$135,000$315,000
450%$150,000$15,000$135,000$450,000
565%$150,000$15,000$135,000$585,000
678%$130,000$13,000$117,000$702,000
788%$100,000$10,000$90,000$792,000
895%$70,000$7,000$63,000$855,000
998%$30,000$3,000$27,000$882,000
10100%$20,000$2,000$18,000$900,000
11Close$0Release $50,000$50,000$950,000
12Final$0Release $50,000$50,000$1,000,000

*Assumes 30-day payment terms


Common Issues & Solutionsโ€‹

Overbilling Concernsโ€‹

IssueRiskSolution
Billing ahead of workOwner dispute, auditTie billing to verifiable milestones
Inflated % completeBack-end cash crunchUse cost-to-cost method
Stored materials abuseRejection, reputationProper documentation

Underbilling Consequencesโ€‹

IssueImpactSolution
Cash flow problemsCan't pay subs/suppliersBill accurately each period
Financing project yourselfProfit erosionTrack actual costs closely
Catch-up billingLooks suspiciousConsistent billing practices

Tips for Accurate Billingโ€‹

  1. Update SOV with change orders โ€” Don't lose money on added scope
  2. Bill monthly without fail โ€” Missing a billing cycle hurts cash flow
  3. Document everything โ€” Photos, logs, correspondence
  4. Track costs in real-time โ€” Know your true % complete
  5. Submit on time โ€” Late pay apps = late payments
  6. Follow up on approvals โ€” Don't wait for checks passively
CPA Insight

Your WIP (Work in Progress) schedule ties directly to billing. Overbilling shows as liability; underbilling shows as asset. Both affect your financial statements and bonding capacity.


Interactive Calculatorโ€‹