Skip to main content
Skip to main content

✅ Quality Inspection Playbook

Standardized inspection process for work-in-place. Catch defects before they're covered up and avoid expensive rework that kills your budget and schedule.


Why Quality Inspections Matter

ImpactWithout InspectionsWith Inspections
Rework costs5–15% of project costunder 2% of project cost
Punch list length500+ items at substantial completionManageable list, no surprises
ScheduleRework delays completionFirst-time quality = on-time delivery
Client satisfactionCallbacks, complaints, disputesSmooth closeout, repeat business
Warranty claimsExpensive post-completion fixesIssues caught and fixed during construction

Roles and Responsibilities

RoleResponsibilities
ForemanSelf-inspect own crew's work before requesting formal inspection
SuperintendentConduct formal quality inspections, document findings, verify corrections
Project ManagerReview inspection reports, monitor trends, escalate systemic issues
Project EngineerMaintain inspection logs, schedule third-party inspections, track deficiencies
SubcontractorsSelf-inspect before requesting acceptance, correct deficiencies per timeline
Third-Party InspectorIndependent inspections per contract (structural, mechanical, electrical, fire)

Types of Inspections

TypeWhenWho InspectsPurpose
Self-inspectionBefore requesting formal inspectionForeman / crewCatch obvious issues before anyone else sees them
In-progress inspectionDuring workSuperintendentVerify work is on track, catch issues early
Hold point inspectionAt defined milestones (before cover-up)Superintendent + A/E or inspectorFormal verification before proceeding
Third-party / specialPer contract or codeLicensed inspector, testing agencyCode compliance, structural, MEP, fire
Pre-punch inspectionBefore owner walkSuperintendentInternal quality check before formal punch list
Final inspectionAt substantial completionOwner / A/EAccept work as substantially complete

Step-by-Step Process

Step 1: Define Hold Points

At project start, identify every point where work must be inspected before it gets covered up or the next phase begins.

Common hold points:

TradeHold PointWhat Gets Covered
EarthworkSubgrade inspectionBuried under foundation
ConcretePre-pour: rebar, embeds, formworkBuried in concrete
ConcretePost-pour: finish, elevation, curingCovered by flooring/finishes
Structural steelConnections, torque, weldsCovered by fireproofing/finishes
FramingRough framing before sheathingCovered by sheathing
MEP rough-inRough plumbing, electrical, HVAC before close-upCovered by drywall
WaterproofingBelow-grade waterproofing before backfillBuried underground
InsulationInsulation before drywallCovered by drywall
Fire stoppingFire-rated penetration sealingConcealed in walls/ceilings
RoofingEach layer before the next is appliedCovered by subsequent layers
Never Cover Without Inspection

Covering uninspected work is one of the most expensive mistakes in construction. Tearing out drywall to inspect rough plumbing costs 10x what the inspection would have cost.

Step 2: Self-Inspection (Before Formal Inspection)

The foreman inspects their own crew's work before calling for formal inspection:

Self-inspection checklist approach:

  1. Review the contract drawings and specs for the area
  2. Walk the area with a checklist (see examples below)
  3. Fix anything you find before calling for inspection
  4. Take photos showing the work is ready
  5. Notify superintendent that the area is ready for formal inspection

Why self-inspect first?

  • Avoids embarrassment — getting failed by the inspector
  • Saves time — inspector doesn't have to come back
  • Builds quality culture — crews take pride in first-time acceptance

Step 3: Formal Inspection

The superintendent (or designated inspector) walks the area:

  1. Bring the right documents — Drawings, specs, approved submittals, checklist
  2. Systematic walk — Go area by area, item by item — don't just scan
  3. Check against drawings — Verify locations, sizes, types, spacing
  4. Check against specs — Verify materials, methods, workmanship standards
  5. Check against submittals — Verify approved products were actually installed
  6. Test functionality — Where applicable (doors open/close, fixtures operate, slopes drain)
  7. Photograph — Document both conforming and nonconforming work
  8. Document findings — Note every deficiency with location, description, and photo

Step 4: Document Findings

For each deficiency found:

FieldDetails
LocationBuilding, floor, room, grid — specific enough to find it
DescriptionWhat's wrong — clear and specific
SeverityCritical (must fix before proceeding), Major (must fix before close-up), Minor (cosmetic, can fix later)
ReferenceDrawing/spec section that defines the requirement
PhotoLabeled photo showing the deficiency
Responsible partyWho needs to fix it
Due dateWhen the correction is due

Deficiency severity levels:

LevelDefinitionTimeline
CriticalSafety issue or structural deficiency — work must stop in this areaFix immediately, re-inspect before any further work
MajorDoes not meet drawings/specs — must be fixed before cover-upFix within 48 hours, re-inspect before proceeding
MinorCosmetic or minor workmanship issueFix before pre-punch walk

Step 5: Correction and Re-Inspection

  1. Notify the responsible party — Written notice with deficiency details
  2. Set a correction deadline — Based on severity and schedule
  3. Responsible party makes corrections — Fix the deficiency
  4. Re-inspect — Verify the correction meets requirements
  5. Document closure — Note the deficiency as corrected, with date and photo
  6. Release the hold — Allow subsequent work to proceed

Inspection Checklists by Trade

Concrete — Pre-Pour Inspection

  • Forms aligned per drawings (location, dimensions, elevation)
  • Forms clean, oiled, and tight (no gaps)
  • Rebar size, spacing, and placement per drawings
  • Rebar clear cover verified (chairs/spacers in place)
  • Rebar tied at all intersections
  • Lap splices correct length and location
  • Embedded items placed per drawings (anchor bolts, sleeves, plates)
  • Blockouts in place (MEP penetrations, floor drains)
  • Waterstop installed (if required)
  • Grade and elevation verified (survey)
  • Formwork adequately braced/shored
  • Concrete mix design approved per submittal
  • Testing agency notified (cylinders, slump, air)

Framing — Before Sheathing

  • Layout matches drawings (wall locations, dimensions)
  • Stud size and spacing per drawings
  • Headers, cripples, and king studs per details
  • Hold-down and anchor bolt locations verified
  • Blocking for fixtures, cabinets, equipment in place
  • Fire blocking installed where required
  • Plumb and straight within tolerance
  • Bearing connections match structural drawings
  • All penetrations sleeved or blocked

MEP Rough-In — Before Close-Up

  • Pipe/conduit routing matches drawings
  • Proper sizing per drawings and specs
  • Supports and hangers at required intervals
  • Correct materials per submittal (pipe type, wire gauge)
  • Firestopping at all rated penetrations
  • Pressure testing complete (plumbing — record results)
  • Insulation on pipes/ducts per spec
  • Electrical boxes at correct heights
  • Grounding and bonding complete
  • Access panels provided where required

Common Mistakes

MistakeConsequenceFix
Inspecting too lateWork is already covered — must tear out to inspectDefine hold points at project start, enforce them
Checklist not specific to the workMiss items unique to this projectCustomize checklists for each project/trade
Not documenting deficiencies"It was fine when I looked at it" — no proofWritten report with photos for every inspection
No re-inspectionDeficiency reported but never verified as fixedAlways re-inspect corrections before proceeding
Foreman skips self-inspectionSuperintendent finds obvious errors — wastes everyone's timeMake self-inspection a mandatory step before formal inspection

Metrics

MetricTargetFrequency
Hold point inspections completed100% before cover-upPer hold point
First-time acceptance rateover 85%Monthly
Open deficienciesZero critical, under 10 majorWeekly
Deficiency correction timeCritical under 24 hrs, Major under 48 hrsPer occurrence
Rework cost as % of projectunder 2%Monthly

ResourceLink
Quality Control GuideFull Guide
Inspection Log TrackerInspection Log
Pre-Pour Concrete ChecklistPre-Pour Checklist
Daily Inspection ChecklistDaily Inspection
Punch List PlaybookPunch List