✅ Quality Control Guide
Quality problems are profit problems. Rework costs 3-5x more than doing it right the first time.
Quality Is Free
Prevention costs less than correction. A good QC program pays for itself many times over.
Why QC Matters
| Issue | Cost |
|---|---|
| Rework | 5-15% of project cost (industry average) |
| Callbacks | Lost profit + crew time |
| Punch list delays | Retention held longer |
| Reputation damage | Lost future work |
| Legal liability | Defect claims |
QC Program Fundamentals
Three Lines of Defense
- Self-Inspection — Crews check their own work
- Supervisory Inspection — Foreman/super verifies
- Independent QC — QC manager or third party
Key QC Documents
| Document | Purpose |
|---|---|
| Quality Plan | Overall QC approach |
| Inspection Checklists | What to verify |
| Deficiency Log | Track issues found |
| Test Reports | Third-party verification |
| Corrective Actions | How issues resolved |
Inspection Process
Pre-Installation
Before work begins:
- Materials match approved submittals
- Prior work ready to receive new work
- Layout verified
- Crew briefed on quality requirements
During Installation
While work progresses:
- Methods per specifications
- Workmanship acceptable
- Dimensions and tolerances correct
- Documentation maintained
Post-Installation
After work complete:
- Final inspection performed
- Punch items identified
- Documentation complete
- Area ready for next trade
Inspection Checklists
Why Use Checklists
- Ensure nothing missed
- Consistent inspections
- Training tool for new staff
- Documentation for disputes
- Basis for punch lists
Creating Effective Checklists
Include:
- Specific items to verify
- Acceptance criteria
- Reference to specs/drawings
- Space for notes/photos
- Inspector sign-off
Sample Inspection Points
Concrete:
- Formwork dimensions and bracing
- Rebar size, spacing, and cover
- Embeds and sleeves located
- Concrete mix design verified
- Finishing and curing
Steel:
- Member sizes correct
- Connections per drawings
- Bolt tightening verified
- Touch-up paint complete
- Fire-proofing coverage
MEP Rough-In:
- Routing per drawings
- Supports and hangers
- Penetration sealing
- Testing complete
- Insulation installed
Finishes:
- Surface preparation adequate
- Materials per submittal
- Application per manufacturer
- Touch-up complete
- Protection in place
Managing Deficiencies
Deficiency Categories
| Category | Response |
|---|---|
| Critical | Stop work, immediate correction |
| Major | Correct before covering/next phase |
| Minor | Add to punch list |
| Cosmetic | Correct at completion |
Deficiency Process
- Identify — Document issue with photos
- Notify — Inform responsible party
- Track — Log in deficiency register
- Correct — Verify corrective action
- Close — Re-inspect and document
Root Cause Analysis
For recurring issues:
- Why did this happen?
- Is it training, materials, or methods?
- How do we prevent recurrence?
- Update procedures if needed
Testing & Inspections
Third-Party Testing
Typically required:
- Concrete cylinder breaks
- Structural steel (AISC)
- Welding (AWS)
- Soil compaction
- HVAC balancing
- Electrical testing
Coordinating Inspections
- Schedule in advance
- Prepare area for inspection
- Have documentation ready
- Be present during inspection
- Get written results
Failed Inspections
If inspection fails:
- Understand the deficiency
- Determine corrective action
- Get approval for repair method
- Complete correction
- Request re-inspection
- Document everything
Quality in Subcontract Management
Pre-Work
- Review quality requirements at pre-con
- Verify crew qualifications
- Confirm material submittals approved
- Establish inspection points
During Work
- Monitor workmanship regularly
- Address issues immediately
- Document deficiencies in writing
- Hold progress payments if needed
At Completion
- Final inspection before approval
- Document any outstanding items
- Withhold retention for punch work
- Verify corrections before payment
Mockups & First-Work Inspections
Why Mockups Matter
- Establish quality standard
- Identify issues early
- Train crews on expectations
- Reference for disputes
First-Work Inspections
Before proceeding with production:
- Inspect first installation
- Get owner/architect approval
- Correct any issues
- Document accepted standard
Preventing Rework
Common Causes of Rework
| Cause | Prevention |
|---|---|
| Unclear documents | Pre-con review, RFIs |
| Poor coordination | BIM, coordination meetings |
| Untrained crews | Quality training, mockups |
| Wrong materials | Submittal verification |
| Missed inspections | Inspection scheduling |
Building Quality Culture
- Make quality everyone's job
- Catch issues early (cheaper to fix)
- No blame culture (focus on improvement)
- Celebrate quality achievements
- Learn from failures
Build Quality In
Free Template: Download our inspection checklist templates.
Track Issues: BLDR Pro tracks quality issues with photos, assigns responsibility, and monitors corrections — ensuring nothing falls through the cracks.