Skip to main content
Skip to main content

✅ Quality Control Guide

Quality problems are profit problems. Rework costs 3-5x more than doing it right the first time.

Quality Is Free

Prevention costs less than correction. A good QC program pays for itself many times over.

Why QC Matters

IssueCost
Rework5-15% of project cost (industry average)
CallbacksLost profit + crew time
Punch list delaysRetention held longer
Reputation damageLost future work
Legal liabilityDefect claims

QC Program Fundamentals

Three Lines of Defense

  1. Self-Inspection — Crews check their own work
  2. Supervisory Inspection — Foreman/super verifies
  3. Independent QC — QC manager or third party

Key QC Documents

DocumentPurpose
Quality PlanOverall QC approach
Inspection ChecklistsWhat to verify
Deficiency LogTrack issues found
Test ReportsThird-party verification
Corrective ActionsHow issues resolved

Inspection Process

Pre-Installation

Before work begins:

  • Materials match approved submittals
  • Prior work ready to receive new work
  • Layout verified
  • Crew briefed on quality requirements

During Installation

While work progresses:

  • Methods per specifications
  • Workmanship acceptable
  • Dimensions and tolerances correct
  • Documentation maintained

Post-Installation

After work complete:

  • Final inspection performed
  • Punch items identified
  • Documentation complete
  • Area ready for next trade

Inspection Checklists

Why Use Checklists

  • Ensure nothing missed
  • Consistent inspections
  • Training tool for new staff
  • Documentation for disputes
  • Basis for punch lists

Creating Effective Checklists

Include:

  • Specific items to verify
  • Acceptance criteria
  • Reference to specs/drawings
  • Space for notes/photos
  • Inspector sign-off

Sample Inspection Points

Concrete:

  • Formwork dimensions and bracing
  • Rebar size, spacing, and cover
  • Embeds and sleeves located
  • Concrete mix design verified
  • Finishing and curing

Steel:

  • Member sizes correct
  • Connections per drawings
  • Bolt tightening verified
  • Touch-up paint complete
  • Fire-proofing coverage

MEP Rough-In:

  • Routing per drawings
  • Supports and hangers
  • Penetration sealing
  • Testing complete
  • Insulation installed

Finishes:

  • Surface preparation adequate
  • Materials per submittal
  • Application per manufacturer
  • Touch-up complete
  • Protection in place

Managing Deficiencies

Deficiency Categories

CategoryResponse
CriticalStop work, immediate correction
MajorCorrect before covering/next phase
MinorAdd to punch list
CosmeticCorrect at completion

Deficiency Process

  1. Identify — Document issue with photos
  2. Notify — Inform responsible party
  3. Track — Log in deficiency register
  4. Correct — Verify corrective action
  5. Close — Re-inspect and document

Root Cause Analysis

For recurring issues:

  • Why did this happen?
  • Is it training, materials, or methods?
  • How do we prevent recurrence?
  • Update procedures if needed

Testing & Inspections

Third-Party Testing

Typically required:

  • Concrete cylinder breaks
  • Structural steel (AISC)
  • Welding (AWS)
  • Soil compaction
  • HVAC balancing
  • Electrical testing

Coordinating Inspections

  • Schedule in advance
  • Prepare area for inspection
  • Have documentation ready
  • Be present during inspection
  • Get written results

Failed Inspections

If inspection fails:

  1. Understand the deficiency
  2. Determine corrective action
  3. Get approval for repair method
  4. Complete correction
  5. Request re-inspection
  6. Document everything

Quality in Subcontract Management

Pre-Work

  • Review quality requirements at pre-con
  • Verify crew qualifications
  • Confirm material submittals approved
  • Establish inspection points

During Work

  • Monitor workmanship regularly
  • Address issues immediately
  • Document deficiencies in writing
  • Hold progress payments if needed

At Completion

  • Final inspection before approval
  • Document any outstanding items
  • Withhold retention for punch work
  • Verify corrections before payment

Mockups & First-Work Inspections

Why Mockups Matter

  • Establish quality standard
  • Identify issues early
  • Train crews on expectations
  • Reference for disputes

First-Work Inspections

Before proceeding with production:

  • Inspect first installation
  • Get owner/architect approval
  • Correct any issues
  • Document accepted standard

Preventing Rework

Common Causes of Rework

CausePrevention
Unclear documentsPre-con review, RFIs
Poor coordinationBIM, coordination meetings
Untrained crewsQuality training, mockups
Wrong materialsSubmittal verification
Missed inspectionsInspection scheduling

Building Quality Culture

  • Make quality everyone's job
  • Catch issues early (cheaper to fix)
  • No blame culture (focus on improvement)
  • Celebrate quality achievements
  • Learn from failures

Build Quality In

Free Template: Download our inspection checklist templates.

Track Issues: BLDR Pro tracks quality issues with photos, assigns responsibility, and monitors corrections — ensuring nothing falls through the cracks.