🏁 Project Closeout Guide
Closeout is where good projects go to die. Don't let poor closeout procedures delay your retention or damage client relationships.
Begin closeout planning at 75% complete. Waiting until the end guarantees delays.
Why Closeout Matters
| Risk | Cost |
|---|---|
| Delayed retention | 5-10% of contract stuck for months |
| Warranty callbacks | Crew returns = lost profit |
| Bad references | Lost future work |
| Legal exposure | Incomplete documentation |
The Closeout Process
Phase 1: Pre-Closeout (75% Complete)
Start planning before substantial completion:
- Review contract closeout requirements
- Identify all required submittals
- Create closeout document checklist
- Assign responsibility for each item
- Set internal deadlines (earlier than contract)
Phase 2: Substantial Completion
Definition: The project is sufficiently complete that the owner can use it for its intended purpose.
To achieve substantial completion:
- Request substantial completion inspection
- Create punch list during walkthrough
- Document any incomplete work
- Obtain certificate of substantial completion
- Start warranty periods
Phase 3: Punch List Management
The punch list is your enemy. Kill it fast.
Creating the Punch List
- Walk every room/area systematically
- Use a standard format (location, item, responsible party)
- Take photos of each item
- Assign to correct trade immediately
Tracking Completion
- Daily punch list status meetings
- Update completion percentages
- Re-inspect completed items
- Don't sign off until truly complete
Common Punch List Delays
- ❌ Waiting on materials (should have been ordered)
- ❌ Subcontractor won't return (enforce contract)
- ❌ Items keep getting added (freeze the list)
- ❌ No one assigned responsibility
Phase 4: Documentation Package
Typical closeout documents required:
Operations & Maintenance (O&M) Manuals
- Equipment manuals
- Maintenance schedules
- Parts lists and suppliers
- Startup/shutdown procedures
As-Built Drawings
- Marked-up construction drawings
- Field changes documented
- Hidden conditions recorded
- MEP routing accurate
Warranties
- Equipment warranties (registered)
- Roofing warranty
- Waterproofing warranty
- Contractor's warranty letter
Certifications & Testing
- Fire alarm certification
- Elevator inspection
- HVAC balancing report
- Electrical testing
- Special inspections sign-off
Administrative
- Final lien waivers (all tiers)
- Consent of surety (if bonded)
- Certificate of occupancy
- Utility transfers
Phase 5: Training & Handover
Don't skip this — it prevents callbacks:
- Schedule training sessions with owner's staff
- Document training with sign-in sheets
- Provide after-hours contact information
- Walk through emergency procedures
Phase 6: Financial Closeout
Retention Release
- Submit all closeout documents
- Request final inspection
- Complete any remaining punch items
- Submit final pay application with retention
- Provide final unconditional lien waivers
- Request retention release in writing
Final Accounting
- All change orders executed
- All subcontracts closed out
- All backcharges resolved
- Final job cost report
- Retention received
Closeout Document Checklist
From General Contractor
- As-built drawings
- O&M manuals (3 copies + digital)
- Warranty compilation
- Final lien waiver
- Consent of surety
- Contractor's warranty letter
From Subcontractors (each)
- Final lien waiver
- Equipment warranties
- O&M sections
- Training documentation
- Spare parts/attic stock
From Authorities
- Certificate of occupancy
- Fire marshal approval
- Health department approval
- Building department sign-off
Common Closeout Problems
Problem: Subcontractor Won't Provide Documents
Solution:
- Hold final payment until received
- Use contract leverage
- Obtain directly from manufacturers if needed
- Document non-compliance
Problem: Punch List Keeps Growing
Solution:
- Formal "punch list freeze" date
- New items become warranty work
- Document everything in writing
- Push back on unreasonable additions
Problem: Owner Won't Sign Off
Solution:
- Request specific written objections
- Propose solutions in writing
- Escalate per contract
- Don't delay other closeout activities
Problem: Missing Warranties
Solution:
- Register equipment during installation
- Track warranty start dates
- Collect from subs before final payment
- Provide what you have, note what's missing
Warranty Administration
During Warranty Period
- Respond promptly to callbacks
- Document each callback
- Determine if warranty or owner damage
- Push to subcontractors when appropriate
Warranty Walkthrough
Many contracts require an 11-month walkthrough:
- Schedule in advance
- Walk entire project
- Create warranty punch list
- Complete before year expires
Get Organized
Free Template: Download our closeout checklist template with all required documents.